Page 18 - AsianOil Week 39
P. 18

AsianOil                                     NEWS IN BRIEF                                           AsianOil







       SOUTH ASIA                             There was a leakage of gas in Gas Terminal   Maari acquisition revised
                                           of ONGC’s Hazira Plant in the early hours of
       GAIL maintains CNG and              24 September 2020. Due to this, a modest fire   long stop date
                                           broke out at around 0300 am.
       D-PNG supplies despite              immediately and started remedial actions to   Jadestone Energy, an independent oil and
                                              ONGC Team in the Plant responded
                                                                                gas production company focused on the Asia
       upstream disruptions                contain the fire. The emergency alarm systems   Pacific region, has agreed with OMV New
                                           were immediately actuated and the Plant was
                                                                                Zealand Limited (“OMV”) to amend the long
       Due to the fire break-out at ONGC Gas   shut down. Large scale depressurizations,   stop date for the Company’s acquisition of
       Processing Plant, Hazira, in the early hours of   due to shut-downs of the units, resulted in   a 69% interest in the Maari Project, shallow
       Thursday, about 30 MMSCMD of natural gas   excessive flaring and blast-like noises.  water offshore New Zealand.
       supplies into GAIL’s north-western pipeline   The affected units of the Plant were isolated   The parties have made substantial progress
       network (HVJ system) was immediately   and depressurized and the Fire was brought   toward satisfying the Acquisition’s closing
       shut-off by the upstream major, to contain any   under control and extinguished in 4 hours, by   conditions, including obtaining the majority
       further damage.                     0735 am on 24 September.  Cooling of the site   of third party consents. As a precautionary
         In the force majeure event triggered by the   was, however, continued for safety.  measure in acknowledgement of the
       ONGC Hazira incident, supply cuts upto 40%   The accident did not cause any casualty or   remaining closing condition, being final New
       against current allocations has been imposed   injury to any person.     Zealand Government regulatory approval,
       on the downstream customers. However,   The boundary wall of the ONGC Plant is   and amidst the New Zealand 2020 general
       uninterrupted supplies are continued to   situated at a significant distance from the site   election, the Company and OMV have agreed
       be maintained to the CGD customers for   of fire. The height and design of the boundary   to revise the long stop date from November
       supporting domestic kitchens (D-PNG) and   wall is such that it prevents the fire to spread   15, 2020 to January 31, 2021.
       public transportation (CNG).        outside and hence insulates nearby areas from   Both parties remain fully committed to the
         GAIL north-western pipeline grid supports   the activities inside.     transaction and the Company continues to
       about 80 MMSCMD and there is no damage   ONGC, September 25, 2020        anticipate closing the Acquisition by the end
       to the network due to the unfortunate incident                           of 2020.Jadestone intends to establish New
       at ONGC facilities at Hazira.                                            Zealand as an extension to its Australia core
         GAIL is committed for safe operation of   SOUTHEAST ASIA               area, and sees the Maari Project as a natural fit
       the pipeline network and is maintaining close                            with its strategy to acquire and reinvest into
       coordination with ONGC teams at the site,   MedcoEnergi successfully     mid-life producing assets.
       towards speedier restoration of natural gas                              JADESTONE ENERGY, September 25, 2020
       supplies through alternative systems.  closed trading period of
       GAIL, September 24, 2020                                                 Mitsubishi to build gas-

       ONGC resumes operations             2020 rights issue                    fired power plant in
                                           Medco Energi Internasional announces that
       in Hazira Plant within a day        it has successfully closed its 2020 Rights Issue   Thailand
                                           trading period. Initial subscriptions were
       after fire                          received from 98% of shareholders, who   Mitsubishi Power, a major subsidiary of the
                                           oversubscribed by 43%. The IDR 1,785 billion
                                                                                Mitsubishi Heavy Industries (MHI), signed
       ONGC worked on war-footing and restored   (~US$122 million) proceeds will be used for   a full turnkey contract for the engineering,
       operations in its Hazira Gas Processing   General Corporate Purposes and working   procurement and construction (EPC) of a
       Plant near Surat within a day after fire. Gas   capital. Further details are available in the   1,400 MW power plant with Hin Kong Power
       supply to consumers has been restored on 25   Prospectus and newspaper disclosures.  Company Limited, an independent power
       September 2020 – a day after the fire.  MEDCOENERGI, September 25, 2020  producer (IPP) in Thailand. Mitsubishi Power
                                                                                will provide two M701JAC gas turbines
                                                                                for the natural gas-fired turbine combined
                                                                                cycle (GTCC) facility. The contract includes
                                                                                a 25-year Long Term Service Agreement
                                                                                (LTSA) for the project. Under this agreement,
                                                                                Mitsubishi Power will provide maintenance
                                                                                on the power plant’s gas turbines to help
                                                                                ensure reliable operations. Commercial
                                                                                operations will begin in March 2024 and
                                                                                January 2025.
                                                                                  The GTCC facility will be built
                                                                                approximately 100 kilometers west of
                                                                                Bangkok. The owner, Hin Kong Power
                                                                                Company Limited, is a special purpose
                                                                                company (SPC) jointly established by RATCH
                                                                                Group Public Company Limited and Gulf
                                                                                Energy Development Public Company
                                                                                Limited, two major IPPs in Thailand. Power



       P18                                      www. NEWSBASE .com                        Week 39   01•October•2020
   13   14   15   16   17   18   19   20