Page 9 - GLNG Week 36
P. 9

GLNG                                         COMMENTARY                                               GLNG




       Restart troubles for





       Australian LNG facilities







       Attempts to restart Prelude FLNG and the second train at

       Gorgon are running into obstacles and taking longer than

       initially expected



        PROJECTS &       ATTEMPTS to restart the second train at Gor-  the repairs and returning Train 2 to service in
        COMPANIES        gon LNG and the Prelude floating LNG (FLNG)  September, but now says it expects the facility to
                         facility – liquefaction capacity that has been  be restarted in October.
       WHAT:             offline in Australia – are running into obstacles.   The company said that following its ongo-
       Chevron and Shell   The challenges illustrate the complexity of the  ing technical work, it was further refining its
       have separately run   projects involved, and while operators Chevron  approach and had decided that some welds in
       into challenges as   and Royal Dutch Shell have sought to downplay  targeted areas would require additional work.
       they attempt to bring   the setbacks, more issues cannot be ruled out  This comes after the Australian Manufacturing
       liquefaction facilities in   before the facilities are back online.  Workers Union said in July that cracks up to 1
       Australia back online.  While the ongoing outages represent a setback  metre long and 30mm deep were found on 8-11
                         to the facilities’ operators, however, the broader  kettles on Train 2. The trade union raised con-
       WHY:              industry may welcome them as it struggles with  cerns that the heat exchangers would need to
       More time is needed   the global glut of LNG, which is still being exac-  be replaced altogether, so while the repairs are
       to bring Gorgon Train 2   erbated by new capacity coming online in the  more extensive than Chevron initially expected,
       back online, while an   US.                            it appears that this is not the worst-case scenario.
       attempted restart of                                    However, there has been speculation that
       Prelude is reported to   Extra time                    welding work on the cracks was initially per-
       have failed.      On September 3, Chevron Australia said it  formed incorrectly, and needed to be redone.
                         would require extra time to complete repairs of  The loss of LNG production as a result of the
       WHAT NEXT:        propane heat exchangers – or kettles – on Train  outage is thought to be costing several million
       The ongoing outages   2 at the Gorgon terminal on Barrow Island, off   dollars per day.
       may be welcomed   the north-west coast of Western Australia. The   Chevron is also due to take Trains 1 and 3
       by the industry as it   super-major discovered cracks in the kettles dur-  offline to inspect the heat exchangers for simi-
       struggles with global LNG   ing routine maintenance on the train that began  lar issues, and now says it hopes that the work
       oversupply.       in May and was subsequently extended to carry  at Train 2 can help those inspections – and any
                         out the necessary repairs.           necessary repairs – to be more efficient. Initially,
                           Chevron had initially anticipated completing  there were suggestions that the entire facility






















                                                                                                  Chevron will stagger
                                                                                                  the closure of the other
                                                                                                  trains at Gorgon.


       Week 36   11•September•2020              www. NEWSBASE .com                                              P9
   4   5   6   7   8   9   10   11   12   13   14