       MIGA issues 20-year guarantees





       for Mozambique’s CTT





        MOZAMBIQUE       THE Multilateral Investment Guarantee Agency  will be injected into the national grid and sold
                         (MIGA) has issued guarantees of 20 years for the  by EDM to Mozambican end-consumers and to
                         450-MW Central Térmica de Temane (CTT)  neighbouring countries under bilateral contracts
                         power generating plant in Mozambique.  or through the Southern African Power Pool.
                           MIGA, an arm of the World Bank Group   The termination payment obligations of
                         (WBG), said on December 21, 2021 that risk  EDM will be guaranteed by the Government
                         guarantees of $251.3mn had been issued to  of Mozambique, represented by the Ministry
                         investors in the plant in northern Inhambane  of Mineral Resources and Energy (MIREME).
                         Province against breach of contract and transfer  Construction is expected to begin in January
                         restriction.                         2022 and operations around November 2024.
                           Contracts issuing guarantees to Globeleq   MIGA said CTT will provide increased
                         Africa Ltd, Moz Power Invest and Sasol Africa  affordable and reliable power, to meet grow-
                         Proprietary Ltd for equity and quasi-equity  ing energy demand in Mozambique, and will
                         investments in CTT were issued on December  increase the generation capacity available for
                         8, 2021.                             export.
                           The natural gas-fired CTT, which is set to be   Support for the project “aligns with the
                         located approximately 30 kilometres south-west  WBG’s Country Partnership Framework and
                         of the town of Inhassoro and about 20 km inland  MIGA’s strategic focus on International Devel-
                         from the coastline of Mozambique, will be an  opment Association countries and conflict-af-
                         independent power producer (IPP).    fected countries,” said MIGA.
                           “The project will be an IPP generating an   The project will increase installed capacity
                         average of 3,143 GWh annually (under current  in a country with a low electricity access rate
                         dispatch assumptions) for sale to Electricidade  and support regional interconnectivity within
                         de Moçambique E.P. (EDM) under a 25-year  Mozambique and neighbouring countries in the
                         tolling agreement,” said MIGA.       Southern Africa region.™
                           MIGA said power produced by the project