Page 11 - AsiaElec Week 44
P. 11

AsiaElec                                   NEWS IN BRIEF                                            AsiaElec







       Indonesian coal mining firms expect global   1 gigawatt by shortening the construction   According to Somesh Kumar, partner and
       coal demand to recover in mid-2021 as   period of substations from six years to three   leader, power and utilities, EY India, tariff
       economies around the world heal from   years and increasing grid access limits from   indexation partially releases the burden on
       COVID-19, even though volumes will remain   10MW to 12MW.                discoms’ financials, whereas it fails to address
       below pre-pandemic levels.             Kepco will also apply different calculation   the issue of long-term tie-up with PPAs.
          Exports are expected to hit 430 million   methods when allocating grids.  “It is imperative to evolve the existing
       tons in 2021, growing 3.6 percent from this   According to Kepco, as renewable energy   power markets which are capable of relieving
       year, but still 8.9 percent below last year’s   facilities rarely utilize 100% of the grid   the discoms from entering into a long-term
       figure, according to Indonesia Coal Mining   capacity, it will now only assign 70% capacity.  contract for power,” he added.
       Association (APBI) estimates.          In its example, Kepco said that 10MW   He said that policymakers have continued
         However, most of next year’s growth is   solar farms would only be allocated a grid   with flat tariffs to provide better recovery
       likely to come in the July-December period,   capacity of 7 megawatts as seldom reach   certainty to developers while inflation indexed
       as countries focus on the distribution of   maximum power output.        tariffs might only help discoms.
       COVID-19 vaccines in the January-June                                      “Renewable tariffs have seen sharp
       period, said APBI deputy chairman Kurnia                                 decline... Since the entire project cost is
       Ariawan.                                                                 sunk, it is not subject to huge inflation either.
         “We think the first half of 2021 will still be   SOL AR                Hence, to provide greater recovery certainty
       highly impacted by the pandemic,” he said at                             to developers and investors, steady tariffs have
       a virtual discussion celebrating APBI’s 31st   Indexed renewables tariffs   been continued by policymakers. Inflation
       anniversary.                                                             indexed tariffs might only help discoms,
         “The second half is when we will see real   could save Indian discoms   which also remains to be seen if they actually
       recovery,” added Kurnia, who is also president                           do,” he added.
       director of coal mining giant PT Kideco Jaya   INR218.bn over five years   According to the report, state-owned
       Agung.                                                                   discoms have not been able to take full
         The COVID-19 pandemic has destroyed   New Delhi: India’s discoms could save up to   advantage of new cheaper renewable energy
       global energy demand over the past year.   INR218.bn over the next five-year period   due to two-part thermal contracts which
       Demand fell so much that the Indonesian   under a partially indexed renewable energy   command a fixed capacity charge even if no
       benchmark coal price (HBA) dropped to a   tariff structure, even if solar tariffs continue to   power is drawn.
       five-year low of $49.42 per ton in September.   fall, according to a recent report.  Typically coal-based power plants have
       For comparison, prices averaged around   This was compared with cash outflows   tariffs in two parts: Fixed charge to recover
       $77.89 per ton last year.           resulting from incremental renewable capacity   fixed cost and variable charge to recover cost
         Demand has recovered in the fourth   auctioned under a flat tariff regime, it added.  of fuel, etc. Since fuel cost varies, developers
       quarter as some economies have reopened,   The report by the Institute for Energy   are given the option of escalation of variable
       which boosted the HBA to $51 per ton in   Economics and Financial Analysis and the   costs based on notified indices.
       October, but experts say prices are unlikely to   CEEW-Centre for Energy Finance said that   In case of renewable energy plants, since
       reach 2019 levels even in 2021.     inflation indexation of tariffs for future solar   the fuel cost is zero and the operational costs
                                           capacity could provide much-needed financial   are minimal, inflation-based indexation has
                                           respite to the distressed discoms helping India   not been prevalent.
                                           move away from coal-fired power.       “Since renewable energy plants, especially
       GRIDS                                  However, this was an interim solution to   utility-scale solar plants were relatively new
                                           ease the unsustainable near-term financial   in India, the financial bodies did not have
       Kepco to build more grids           pressure on discoms.                 confidence in their operation. Hence, a

       to meet demand from

       renewable energy facilities

       Korea Power Corp. (Kepco) will construct
       power grids in regions where renewable
       energy facilities are expected to be built,
       including the counties of Shinan and
       Yeonggwang in South Jeolla. Province.
         Kepco has been implementing a policy
       since October 2016 of guaranteeing access to
       power grids for renewable energy facilities of
       1 megawatt or smaller.
         However, the concentration of 14.4GW of
       renewable energy facilities in specific regions
       resulted in power grid shortages of 4.2GW.
         According to a Kepco official, the state-run
       utility will address the shortage of 3.2GW by
       next year.
         It would further solve the shortage of



       Week 44   04•November•2020               www. NEWSBASE .com                                             P11
   6   7   8   9   10   11   12   13   14