Page 4 - NorrthAmOil Week 43 2021
P. 4

NorthAmOil                                    COMMENTARY                                          NorthAmOil




       Venture Global makes progress





       ahead of Calcasieu Pass start-up







       Venture Global LNG is preparing to begin commissioning on its Calcasieu Pass

       liquefaction plant in Louisiana after striking three supply deals with China’s Sinopec



        US GULF COAST    US-BASED Venture Global LNG is making  Momentum
                         advances at both its Calcasieu Pass facility, which  At Calcasieu Pass, Venture Global has requested
       WHAT:             is due to enter commercial service soon, and its  permission from US regulators to begin com-
       Venture Global has   proposed Plaquemines terminal – both on the  missioning liquefaction systems. The company
       asked regulators for   Louisiana Gulf Coast. The company’s progress  told the US Federal Energy Regulatory Com-
       permission to begin   appears to be driven in part by three deals with  mission (FERC) in a filing last week that the
       the commissioning of   China’s Sinopec, details of which emerged last  environmental conditions required to begin
       liquefaction systems at   week. (See NorthAmOil Week 42)  commissioning had been met, and that it was
       Calcasieu Pass LNG.  On October 19, the US Department of Energy  therefore seeking permission to proceed. Once
                         (DoE) made public a letter showing that Ven-  permission is granted, the facility would start
       WHY:              ture Global had signed two 20-year supply deals  producing LNG in test mode later this year,
       The terminal is due to   with Sinopec, for a combined 4mn tonnes per  before entering commercial service in 2022.
       begin producing LNG in   year (tpy) of LNG. Both deals involve supply   Days later, Reuters reported that Venture
       test mode this year before   from Plaquemines. Two days later, details of a  Global had also asked the FERC for permission
       entering commercial   further deal between Venture Global and Sino-  to start early work at the site of the Plaquem-
       service in 2022.  pec’s Unipec trading arm – for 1mn tpy of LNG  ines terminal. The company is reported to have
                         to be supplied from Calcasieu Pass – emerged  asked for permission by November 25 to start
       WHAT NEXT:        in a separate letter from the US company to the  installing piles and pile caps for the heavy haul
       The company has also   DoE.                            bridge at the site. The bridge will allow for heavy
       requested permission to   Venture Global itself has not commented on  modules to be transported to the site from off-
       begin early work on its   the deals, but in the subsequent days, the com-  loading facilities on the Mississippi River.
       proposed Plaquemines   pany was reported to be moving forward with   This comes ahead of a final investment deci-
       LNG terminal.     plans for both Calcasieu Pass and Plaquemines.  sion (FID) on Plaquemines that is being targeted





































       P4                                       www. NEWSBASE .com                        Week 43   28•October•2021