       BP starts new drilling projects




       in Caspian Sea





        AZERBAIJAN       BP has started drilling the A22z appraisal well at  was delivered to the location in December
                         the Azeri-Chirag-Guneshli block of fields. "The  2022. The depth of the well is expected to be
       BP is assessing ACG’s   purpose of drilling this well is to obtain informa-  about 7 kilometres," BP-Azerbaijan said in a
       deep layers.      tion about deep gas reservoirs (deep-gas) of the  statement. Drilling the well will take about a
                         ACG block. The A22z well will be drilled from  year.
                         the Chirag platform and through the lateral   “However, it is possible that this period will
                         mouth of the existing gas injection well A22 will  take longer if a test programme is carried out
                         enter deep gas reservoirs on the southern flank  to evaluate the results. Deep horizons located
                         of the ACG structure," BP-Azerbaijan said in a  below the productive strata are currently being
                         statement.                           exploited on the eastern wing of the field," the
                           According to the company, the depth of the  information says.
                         well will be up to 4.5 kilometers. "If the drilling   The contract for the development of the
                         is successful, the information obtained from the  Azeri, Chirag, and deepwater Gunashli fields
                         well will provide a broader understanding of the  was signed on September 20, 1994, and entered
                         structure of the area and the pressures in deep  into force on December 12 of the same year. This
                         layers," the information says.       agreement expires in 2024. However, on Septem-
                           According to BP's plans, drilling of the well  ber 14, 2017, a new contract for the development
                         will take about three months. After that, an  of the ACG block, calculated until 2050, was
                         extensive logging programme and the instal-  signed in Baku.
                         lation of gauges to record pressure data are   Under the new contract, the share of British
                         planned for the well. As reported, deep-gas  BP (project operator) is 30.37%, SOCAR (25%),
                         reserves at ACG are currently projected at 300  Hungarian MOL (9.57%), American Exxon-
                         bcm.                                 Mobil (6.79%), Indian ONGC Videsh (2.31%),
                           BP has also started drilling a new explora-  Japanese Inpex Corp. (9.31%) and ITOCHU Oil
                         tion well SDX-8 at the Shah Deniz field in the  (3.65%), Norwegian Equinor (7.27%), Turkish
                         Azerbaijani sector of the Caspian Sea. "Drill-  TPAO (5.73%). ACG is currently the largest oil
                         ing of the well is carried out from the Heydar  field in Azerbaijan, it provides 2/3 of the coun-
                         Aliyev semi-submersible drilling rig, which  try's oil production. ™



       Week 04   25•January•2023                www. NEWSBASE .com                                             P15