AsiaElec                                        NUCLEAR                                             AsiaElec


       South Korea issues permit




       for Shin Hanul 1 reactor




        SOUTH KOREA      SOUTH Korea’s nuclear safety regulator has  related to the application were discussed during
                         given its conditional approval for the start-up  a total of 18 meetings. On-site inspections were
                         of unit 1 at Korea Hydro & Nuclear Power’s  carried out by the NSSC in late February this
                         (KHNP) Shin Hanul nuclear power plant (NPP).  year.
                           The Nuclear Safety and Security Committee   “In the future, the NSSC plans to thoroughly
                         (NSSC) set a number of requirements for addi-  check the safety of nuclear fuel loading and test
                         tional safety measures at the unit, the first of two  operation, which will be carried out following
                         APR-1400 reactors at the site.       the Shin Hanul unit 1 operation permit, through
                           Ground breaking for the first two units at the  pre-use inspections,” the regulator said.
                         Shin Hanul site took place in May 2012.  The APR-1400 is an evolutionary pressurised
                           First concrete for unit 1 was poured two  water reactor with its origins in the CE System
                         months later, with that for unit 2 following in  80+ model. Principally designed by Korea Engi-
                         June 2013.                           neering Co., it produces 1,400 MWe and has a
                           The 1,350-MW pressurised water reactors  60-year design life. It supersedes the standard-
                         (PWRs) were originally scheduled to enter ser-  ised 995 MWe OPR-1000 design, of which South
                         vice in April 2017 and April 2018.   Korea built 12.
                           Fuel loading in unit 1 had been scheduled for   The APR-1400 features improvements in
                         June 2019 but was delayed pending safety checks  operation, safety, maintenance and affordabil-
                         by the NSSC and some modifications. Commer-  ity based on accumulated experience as well as
                         cial operation of unit 1 was then anticipated in  technological development. Design certification
                         July 2021, and unit 2 in May 2022, but there have  by KINS was awarded in May 2003. In October
                         been further delays.                 2017, European Utility Requirements – a tech-
                           KHNP applied for an operating licence for  nical advisory group for European utilities on
                         Shin Hanul 1 in December 2014.       NPPs – approved the APR1400 reactor design.
                           In considering the application, the NSSC  The US Nuclear Regulatory Commission certi-
                         went through a review by the Korea Institute of  fied the APR-1400 in August 2019, finding the
                         Nuclear Safety (KINS). A pre-use inspection of  design had fully met US safety requirements.
                         the unit was made in May 2020. A preliminary   Four APR-1400s have also been built at Bar-
                         review by a specialised committee was carried  akah in the United Arab Emirates. The first of
                         out between June and October last year. The  these units started commercial operation in
                         NSSC said it started assessing the application at  April and unit 2 has completed fuel loading and
                         an official meeting in November. Major issues  is being prepared for start-up.™






































       Week 28  14•July•2021                    www. NEWSBASE .com                                              P7