                                                                                                  Bulgarian PM Boyko
                                                                                                  Borisov and Serbian
                                                                                                  President Alexander
                                                                                                  Vucic inspect the
                                                                                                  construction site.



























       Bulgaria still on track to finish




       TurkStream extension in 2020





        BULGARIA         BULGARIA aims to wrap up work on its sec-  being delivered to these bases on a daily basis.
                         tion of the Balkan Stream, an extension of Rus-  Neighbouring Serbia finished its 403-km sec-
       Bulgaria has been   sia’s TurkStream gas pipeline, by the end of this  tion of the Balkan Stream in late March, although
       blamed by Russia for   year, despite the coronavirus (COVID-19) crisis,  it is still working on support infrastructure.
       stalling on the project.  Prime Minister Boyko Borissov said on June 1.  Meanwhile, Hungary plans to triple the
                           Balkan Stream will pump TurkStream gas  capacity of a pipeline link with Slovakia by 2024
                         through Bulgaria and Serbia and into Hun-  to 5bn cubic metres (bcm) per year, in order to
                         gary, enabling Russia to cut transit volumes via  carry gas from Balkan Stream, the country’s for-
                         Ukraine and potentially boost sales in Europe.  eign minister, Peter Szijjarto, said on June 2.
                           Bulgaria had initially said it would complete
                         its 474-km stretch of the pipeline by the end  Greek deal
                         of 2019. But work was slow to start because of  Another key market for Russian gas in southeast
                         delays finalising the award of a €1.1bn ($1.2bn)  Europe is Greece. Gazprom announced on June
                         construction contract to Saudi-led group Arkad.  1 it had struck a new 10-year gas supply deal with
                         State gas grid operator Bulgartransgaz did not  Greek industrial conglomerate Mytilineos.
                         secure financing to cover advanced payments   The Russian gas exporter did not say how
                         until late October. The delays irked Moscow,  much gas the contract covered. But it has been
                         with Russian President Vladimir Putin accusing  supplying Mytilineos since 2017 and sold the
                         Sofia in December of intentionally obstructing  company 588mn cubic metres (mcm) of gas last
                         the project.                         year.
                           “Despite the coronavirus, no matter how   “The co-operation between Gazprom Export
                         difficult it was, work has not stopped on ... the  and Mytilineos proves the demand for Rus-
                         Balkan Stream,” Borissov told reporters after  sian gas in the Greek market and will further
                         inspecting construction with Serbian President  strengthen the interaction between our coun-
                         Alexander Vucic. “Let’s hope that coronavirus is  tries in the energy sector,” Gazprom Export head
                         gone. And despite two to three months’ delay we  Elena Burmistrova said in a statement.
                         hope to meet the timeline and have it ready by   Mytilineos is involved in various activities,
                         the end of the year.”                including gas and electricity trade, power gener-
                           According to a government statement,  ation and metallurgy.
                         around 91.4 km of pipes have been positioned   Gazprom’s overall sales to Greece came to
                         in prepared trenches. The remainder are either  2.4 bcm per year, down 26.7% versus the level
                         at temporary construction bases along the pipe-  in 2018, partly because of stiff competition from
                         line’s route, or are at the port of Bourgas and  LNG suppliers. ™