       ONGC reportedly facing new delays at




       KG-DWN-98/2 deepwater development




        PROJECTS &       INDIA’S Oil and Natural Gas Corp. (ONGC)  followed by overall project completion by May
        COMPANIES        is reportedly facing more delays at its Cluster-2  2023.
                         fields in the Krishna Godavari (KG) Basin’s deep-  One of the sources was reported as saying the
                         water KG-DWN-98/2 development. The $5bn  CPP and living quarters facility was the project
                         development, which is also known as KG-D5, is  element facing the most challenges. The facility is
                         the largest subsea project in India.  due to be supplied by India’s Afcons and Malay-
                           Citing sources familiar with the matter,  sia’s Sapura Energy and it has been suggested that
                         Upstream reported last week that the project  the latter’s financial difficulties are exacerbating
                         was set to be delayed by several months. This is  the delays.
                         the result of four key elements running behind   Cluster-2 was initially expected to produce
                         schedule. These are reported to be the supply of a  first gas in 2019, followed by first oil in 2020.
                         central processing platform (CPP), an integrated  Indian media previously reported that defer-
                         subsea production system and subsea umbilical  ments in awarding contracts for the project had
                         riser and flowlines, a leased floating produc-  resulted in start-up dates being pushed back even
                         tion, storage and offloading (FPSO) vessel and  before the onset of the coronavirus (COVID-19)
                         onshore processing facilities.       pandemic, which further added to delays at the
                           The delays to these elements have been  development.
                         attributed to coronavirus (COVID-19) restric-  Nonetheless, a gas well entered production at
                         tions, engineering changes and challenges with  the KG-DWN-98/2 block in 2020, followed by a
                         project execution. ONGC had previously been  second gas well in August 2021.
                         expected to begin production from the Cluster-2   Block KG-DWN-98/2 is anticipated to have
                         project in the April 2021-March 2022 financial  total peak gas production of around 16mn cubic
                         year. However, according to Upstream, the com-  metres per day and peak oil output of 80,000 bar-
                         pany now anticipates first oil in December 2022,  rels per day (bpd).™


                                                  SOUTHEAST ASIA

       Pertamina makes gas discovery at Mahakam





        PROJECTS &       A subsidiary of Indonesia’s Pertamina has made  660,000 bpd of oil in 2021, Tasrif told a con-
        COMPANIES        a natural gas discovery in the Mahakam block  ference on January 12, falling just short of a
                         offshore East Kalimantan. Pertamina Hulu  target of 668,000 bpd and declining 6.6% from
                         Mahakam said the Manapatu 1x exploration well  707,000 bpd in 2020.
                         had struck 207 of net oil and gas pay at a depth   Gas lifting also declined slightly year on year,
                         of 3,776 metres.                     reaching 982,000 barrels of oil equivalent per
                           The discovery was made in December, and  day in 2021, compared with 983,000 boepd the
                         the first drill stem test was carried out on January  previous year.
                         3, with the well flowing 15mn cubic feet (424,800   “If you look at the downward trend, it is
                         metres) per day of gas and 500 barrels per day  indeed declining because we don’t have new
                         (bpd) of condensate.                 sources,” Tasrif said. “Our wells are old. There is
                           More flow tests will be carried out to assess  limited output”.
                         the full potential of the well, which would be tied   This year, the country is aiming to raise oil
                         into existing production infrastructure if Per-  lifting to 703,000 bpd, and Tasrif said higher
                         tamina goes ahead with its development. The  demand and newly discovered oil reserves were
                         well is targeting the Mentawir and Tanjung Batu  expected to help increase lifting.
                         formations.                            “We have a roadmap to optimise existing
                           The find is a welcome one for Indonesia as  fields, [increase] oil and gas recovery with
                         the country struggles to turn around declin-  enhanced oil recovery [EOR], and massive new
                         ing oil and gas production and attract new  exploration,” he said.
                         investors. This week, Indonesian Minister for   Indonesia is targeting 1mn bpd of oil produc-
                         Energy and Mineral Resources Arifin Tasrif  tion and 12bn cubic feet (340mn cubic metres)
                         said the country’s ready-to-sell oil output had  per day of gas by 2030, and recently estimated
                         fallen for a fifth straight year in 2021, narrowly  that $187bn of investment would be required to
                         missing its target for the year. Indonesia lifted  meet these goals.™