Page 7 - AfrElec Week 35
P. 7

AfrElec                                          ESKOM                                               AfrElec
































       Eskom warns of more power cuts





        SOUTH AFRICA     SOUTH Africa’s Eskom said on September 2   Eskom also said that another key factor that
                         that it had raised its load-shedding programme  needed to be considered was the fact that the
                         to Stage 4, as the company was forced to take  building of Medupi was contrary to how other
                         power stations offline in order to prevent the  projects are approached around the world.
                         grid collapsing.                       “Globally projects are not built the way
                           Eskom said that the power system was  Eskom approached Medupi, but are built one
                         severely constrained, and that cold winter  unit a time. Ideally in the South African context,
                         weather was placing extra demand on the grid.  a comprehensively defined greenfield project
                           The company said that unplanned break-  should take approximately 5 years in develop-
                         downs now amounted to 11,300 MW, and that  ment,” it said.
                         5,040 MW was offline for planned maintenance.  “The results of poor pre-planning due to late
                           It said that it had successfully returned a gen-  start decisions are detrimental to project execu-
                         eration unit each at the Tutuka, Komati, Hend-  tion. Repeatability and forward planning can
                         rina and Camden power stations. Two additional  produce better cost and schedule certainty.”
                         units, however, had suffered breakdowns at the   Eskom said that it had recognised from the
                         Matla and Kriel power stations.      beginning of the new-build programme that
                           Meanwhile, Eskom officials told the South  there were not enough engineers who could
                         African Parliament that load-shedding could  adequately execute “Medupi, Kusile, Return to
                         continue until 2022.                 Service Units and Gas projects at the same time.”
                           In a written submission to Parliament’s Stand-  Eskom also pointed to corruption in the
                         ing Committee on Appropriations, the company  building process. For example, a former Kus-
                         also explained while construction of the Medupi  ile senior manager was arrested for allegedly
                         and Kusile coal-fired power plants was way  receiving millions from a ZARR45mn ($43mn)
                         behind schedule.                     contract.
                           While Medupi is set to be completed at the   “Delays [have been] caused as a result of
                         end of 2020, work on the Kusile power station  modifications to critical contracts not being pos-
                         will be done in 2023.                sible due to these contractors being investigated
                           The power utility has cited unforeseen cir-  for alleged corruption,” it said.
                         cumstances as part of the reason it incurred cost   Indeed, Eskom itself is to take the Gupta
                         overruns. Those include strike action, which in  family to court for to recoup at least ZARR3.8bn
                         total has lasted 18 months. Eskom has also said  ($212mn) from former Eskom directors, execu-
                         there were welding issues which had led to an  tives, contractors and consultants, and a former
                         eight-month delay.                   government minister.
                           “Given the inadequate time to plan, absence   The action is being taken by current Eskom
                         of suitable resources in the country (in quantum  management, which claims that people close to
                         and skill) and other consequential issues, Eskom,  the Gupta family and companies it ran siphoned
                         in an overly optimistic way, endeavoured to  off the cash during their purchase in 2015 of
                         manage a programme of this magnitude for the  Optimum Coal Holdings (OCH), a major coal
                         benefit of the country,” the utility added.  supplier to Eskom, from Glencore.™




       Week 35   03•September•2020              www. NEWSBASE .com                                              P7
   2   3   4   5   6   7   8   9   10   11   12