Page 8 - DMEA Week 05 2022
P. 8

DMEA                                            REFINING                                               DMEA


       NNPC report says Port Harcourt




       rehabilitation project is behind schedule






        AFRICA           NIGERIAN National Petroleum Corp. (NNPC)  said in the report that Tecnimont was in com-
                         has said that its effort to rehabilitate Port Har-  pliance with the provisions of local content laws.
                         court Refining Co. (PHRC) is running behind  The Italian contractor is actively hiring Nigerian
                         schedule.                            companies to act as sub-contractors, in line with
                           The local Punch daily said it had viewed a  the provisions of the Nigerian Content Develop-
                         report from NNPC stating that cumulative pro-  ment Act, it said.
                         gress on the project should have amounted to   PHRC is comprised of a 60,000 bpd unit built
                         10.7% by this date. So far, though, the rehabilita-  in 1965, known as Area 5, and a newer unit built
                         tion project is only 6.3% complete, and the gov-  in 1989 which is capable of processing 150,000
                         ernment-owned company said in the report that  bpd of crude.
                         it had ordered its contractor, the Italian company   Tecnimont was hired on an engineering,
                         Tecnimont, to close the gap.         procurement, construction, installation and
                           “[The] contractor is to issue a mitigation plan  commissioning (EPCIC) contract worth nearly
                         to address this variance and to ensure that the  $1.6bn. It has already received an advance pay-
                         project is completed within schedule,” the report  ment of 15% of this sum, with $194mn or 70% of
                         said, according to Punch.            the total coming in US dollars and the remain-
                           Tecnimont is supposed to complete the reha-  ing 30% in naira, in line with the terms of its
                         bilitation of the 210,000 barrels per day (bpd)  contract.
                         PHRC complex by early January of 2025, 44   The Italian company had carried out a
                         months after the date that its contract took effect  $50mn, six-month ‘integrity check’ in 2019, with
                         – April 6, 2021.                     fellow Italian firm Eni contracted as technical
                           However, it has encountered a number of  adviser. This work included equipment inspec-
                         delays as a result of worldwide supply chain  tion at the site, as well as “relevant engineering
                         disruptions and the coronavirus (COVID-19)  and planning activities”.
                         pandemic, including the latest outbreak of the   NewsBase understands that only once work
                         omicron variant, according to refinery staff  to rehabilitate PHRC has been completed can
                         cited in the NNPC report. The news casts further  NNPC proceed with similar projects to revamp
                         doubt on the project’s ability to rehabilitate 90%  facilities at Warri and Kaduna that have capaci-
                         of the refinery’s by the end of next year.  ties of 125,000 bpd and 110,000 bpd respectively.
                           Additionally, it has also experienced chal-  Contracts were awarded to Italy’s Saipem and
                         lenges as a result of problems with Nigeria’s  subsidiary Saipem Contracting worth a total of
                         East-West Road Corridor, which has hindered  $1.485bn – $898mn for Warri and $587mn for
                         movements to and from the refinery and caused  Kaduna – in August that entail a three-phase
                         the loss of many project man-hours.  approach to rehabilitate the refineries over 77
                           On a more positive note, however, NNPC  months.™

































       P8                                       www. NEWSBASE .com                       Week 05   03•February•2022
   3   4   5   6   7   8   9   10   11   12   13