Page 14 - AfrElec Week 16 2021
P. 14

AfrElec                                     NEWS IN BRIEF                                             AfrElec







       World’s longest power               Science and Technology (NUST). The team   uptake agreement has been completed
                                           of foreign engineers recruited to conduct the
                                                                                with the Zimbabwe Electricity Distribution
       transmission cable to               study could not travel to Zimbabwe,” adds   Company (ZETDC). “The company obtained
                                                                                independent power producer (IPP) licenses
                                           Graciano Takawira, president of Pragma Leaf
       connect Morocco, UK                 Consulting.                          for the solar power projects for each operating
                                                                                location. The company is progressing with
                                              As part of the project, we have also signed
       The UK-based renewable energy solutions   agreements with ‘South African company   selecting an EPC contractor whilst awaiting
       company Xlinks is planning on connecting   Co-Ash Resources, which has contacted   finalisation of power purchase agreements
       Morocco and the UK with a 3,800-kilometer   French companies Satarem, Amre Holdings   with ZETDC,” he said.
       underwater electricity transmission cable.  and Siemens for the project. We have also   Meanwhile, RioZim has revealed that its
         Xlinks is planning to build a 10.5 gigawatt   partnered with the Dutch company Geo   2800MW Sengwa Power Station has been
       (GW) of renewable energy complex in   Power, which is expected to invest $50mn in   constrained by funding issues. “The efforts
       Morocco, to harvest both wind and solar   solid waste to energy in Bulawayo. Covid-19   to secure financing to commence Phase 1 of
       energy. It will link to a 5 GW/20 GWh   makes it impossible for technical teams to   the project were significantly hampered by
       (gigawatt hours) storage unit in the country.   move around,” says Graciano Takawira,   the uncertainties presented by the Covid-19
       In turn, this energy will be sold to the UK   president of Pragma Leaf Consulting.  pandemic,” said Mr Beebeejaun. He further
       through the high-voltage direct current   Read Also Urban sanitation, a major   added that the company is focused on
       (HVDC) transmission cable, connecting   challenge for sustainable cities in Africa  advancing the financing arrangements in
       Morocco to several locations in Wales and   The UK-based company had planned to   order to make positive progress on the power
       Devon, UK.                          start construction of the Bulawayo waste-  station. RioZim, through Rio Energy Ltd,
         Xlinks CEO Simon Morrish explained   to-energy plant in 2020. The new challenge   owns coal mining claims at Sengwa in Gokwe.
       to pv magazine that the company is already   is to complete the raising of the necessary   The Sengwa Coal Deposit is situated in
       in “discussions with Moroccan community   funds for the project, amounting to $150mn.   North Western Zimbabwe, 450km from
       leaders and government regarding the   The project will process 325 tonnes of waste   Harare, with proven ore reserves in excess
       exact sites of the solar farm and working on   per day, generating 78,000-110,000 litres of   of 525mn tonnes. The power station project
       permitting with the relevant departments.”   biodiesel per day, 60 m3 of biogas and 11.35   is based on a coal resource of 1.3bn tonnes,
       Morrish explained that the total energy will   MW of electricity.        capable of generating up to 2,000MW of
       consist of 7 GW for solar and 3.5 GW for                                 power, almost as much as Zimbabwe’s total
       wind capacity.                      SOL AR                               installed capacity.
         The CEO hopes that the first 1.8 GW cable                                The proposed project envisages the
       will be active in the beginning of 2027, while   Construction of 178MW   construction of a number of smaller power
       the second cable should launch in 2029. The                              plants over the next ten years. In order
       3,800-kilometer cable will consist of four   RioZim solar power plant to   to achieve this goal, RioEnergy is in the
       cables in total, and will make up the longest                            process bringing in technical partners to help
       underwater power transmission link in the   begin soon                   construct the power station.
       world.
         The underwater cable will cross the   Construction of the 178MW RioZim solar
       territorial waters of France, Portugal, and   power plant in Zimbabwe is set to begin soon.
       Spain, on four separate occasions.  The company is currently in the process of
                                           selecting an EPC (engineering, procurement
                                           and construction) contractor for the project.
                                              According to RioZim chairman Rashid
       WASTE-TO -ENERGY                    Beebeejaun, the RioZim solar power plant
                                           project will commence once an energy
       Zimbabwe waste-to-energy

       project delayed again

       The Bulawayo solid waste-to-energy project in
       Zimbabwe is delayed again, after many false
       starts. This time the delay is caused by travel
       restrictions due to the Covid 19 pandemic.
         According to Graciano Takawira,
       president of Pragma Leaf Consulting (Pvt),
       the company developing the project, only the
       basic engineering design (FEED) has been
       completed. This part of the project involves
       updating the characterisation of the waste in
       Bulawayo City, as well as the environmental
       impact assessment (EIA) of the future facility.
       “To complete this study, we were obliged
       to engage the Department of Chemical
       Engineering at the National University of



       P14                                      www. NEWSBASE .com                           Week 16  22•April•2021
   9   10   11   12   13   14   15