Connectivity Process  Connectivity Process


 Fibre Order Process  Wireless Microwave Order Process




 Fibre = 4-6 months  Wireless = 2-6 weeks



 01  Order Submitted To The Supplier  01  Order Submitted To The Supplier






 02  Order Accepted By Supplier  02  Order Accepted By Supplier
                                 (Circuit Number Issued)
 (Circuit Number Issued)



 03  Site Survey  03             Site Survey







 04  Wayleaves    04             Link Installation






 05  Build Kick-Off Meeting  05  Link Connection & Soaking






 06  Civils       06             Handover






 07  Optical Build  07           Internet Access Installation






 08  Link Connection & Soaking







 09  Handover






 10  Internet Access Installation