Page 5 - Ironworkers Memorial Bridge Project
P. 5
Project Schedule
Variable timeline
MOBILIZATION OCT. 2020, PIER 10-11 COATING AND INSTALL TEMPORARY BIRD COATING AND STEEL REPAIRS BETWEEN
STEEL REPAIRS, EXCLUSION NETTING PIERS 11 AND 15,
BETWEEN PIER 11 – 15,
INSTALL TEMPORARY BIRD COATING AND STEEL REPAIRS
EXCLUSION NETTING BETWEEN PIERS 15 - 17
BETWEEN PIER 15 - 17, AND