Page 8 - A:STPAGE2.PDF
P. 8

EM 1110-2-2300
        31 Jul 94

        developed. All of the project OMRR&R and dam safety      e. Construction phase. This phase includes prepa-
        requirements should be identified and discussed with the  ration of P&S for subsequent construction contracts,
        sponsor and state during the feasibility phase. A turnover  review of selected construction contracts, site visits, sup-
        plan for non-Federal dams that establishes a definite turn-  port for claims and modifications, development of opera-
        over point of the dam to the sponsor should be docu-  tion and maintenance (O&M) manuals, and preparation
        mented in the initial project management plan and in the  and maintenance of as-built drawings. Site visits must be
        feasibility report. The turnover of the dam should occur  made to verify that conditions match the assumptions used
        immediately following the first periodic inspection. Ade-  in designing the project features. Site visits may also be
        quate engineering data must be obtained and analyzed and  necessary to brief the construction division personnel on
        sufficient design performed to define the appropriate level  any technical issues which affect the construction. The
        of risk associated with the contingencies assigned to each  O&M manual and water control manual will be completed
        cost item in the estimate (ER 1110-2-1150).          and fully coordinated with the local sponsor during this
                                                             phase of the project. As-built drawings are prepared and
            d. Preconstruction engineering and design phase.  maintained by engineering during the construction phase
        During the preconstruction engineering and design (PED)  (ER 1110-2-1150).
        phase, it may be determined that a GDM is necessary
        because the project has changed substantially since admin-  f.  Operation and maintenance phase. The project
        istration review of the feasibility report (with engineering  is operated, inspected, maintained, repaired, and rehabili-
        appendix) or authorization, the project was authorized  tated by either the non-Federal sponsor or the Federal
        without a feasibility report, there is a need to readdress  Government, depending upon the project purposes and the
        project formulation, or there is a need to reassess project  terms of the project cooperation agreement (PCA). For
        plans due to changes in administration policy (ER 1110-2-  PCA projects and new dams turned over to others, the
        1150 will be followed). For a complex project such as a  Corps needs to explain up front the O&M responsibilities,
        dam, results of the engineering studies for individual  formal inspection requirements, and responsibilities to
        features of the project such as the spillway, outlet works,  implement dam safety practices. Periodic inspections will
        embankment, and instrumentation will be submitted in  be conducted to assess and evaluate the performance and
        separate design memorandums (DMs) with sufficient    safety of the project during its lifetime. Modifications to
        detail to allow preparation of plans and specifications  the features of a project which occur during the operating
        (P&S) to proceed during the review and approval process.  life of a project will be reflected in the as-built drawings
        Contents and format of a DM are given in ER 1110-2-  (ER 1110-2-1150).
        1150, Appendixes B and D, respectively. A significant
        level of geological investigation and exploration and stud-  2-3. Types of Embankment Dams
        ies on the availability of construction materials are accom-
        plished to support the DM. While final design parameters  a.  Introduction.  The two principal types of
        are not selected at this stage of design, it is necessary that  embankment dams are earth and rock-fill dams, depending
        the testing for engineering properties of materials and  on the predominant fill material used. Some generalized
        hydraulic model testing that may be necessary for the  sections of earth dams showing typical zoning for differ-
        project be in progress. In preparation for the beginning of  ent types and quantities of fill materials and various meth-
        each major construction contract, engineering will prepare  ods for controlling seepage are presented in Figure 2-1.
        a report outlining the engineering considerations and  When practically only one impervious material is avail-
        providing instructions for field personnel to aid them in  able and the height of the dam is relatively low, a
        the supervision and inspection of the contract. The report  homogeneous dam with internal drain may be used as
        will summarize data presented in the engineering appen-  shown in Figure 2-1a. The inclined drain serves to pre-
        dix to the feasibility report but will also include informal  vent the downstream slope from becoming saturated and
        discussions on why specific designs, material sources, and  susceptible to piping and/or slope failure and to intercept
        construction plant locations were selected so that field  and prevent piping through any horizontal cracks travers-
        personnel will be provided the insight and background  ing the width of the embankment.  Earth dams with
        necessary to review contractor proposals and resolve  impervious cores, as shown in Figures 2-1b and 2-1c, are
        construction problems without compromising the design  constructed when local borrow materials do not provide
        intent (ER 415-2-100). Format of the report on engineer-  adequate quantities of impervious material.  A vertical
        ing considerations and instructions for field personnel is  core located near the center of the dam is preferred over
        given in Appendix D of ER 1110-2-1150.               an inclined upstream core because the former provides




        2-2
   3   4   5   6   7   8   9   10   11   12   13