Scope of Works - Mitre House, Kings Rd (614)
    614 Mitre House, 124 Kings Road, London SW3 4TP
Refurbishment of the Common Parts
 3.6.7 3.6.8 3.6.9 3.6.10
The contractor is to rub down, prepare and decorate the 2no sections of timber panelling to either side of the lobby doors in colours to be agreed with the client.
The sticky pads and fire extinguisher hangers are to be removed from the walls. Fixing holes are to be filled ready for redecoration.
All cabling is to be tested and redundant cabling removed. The remainder of cabling is to be boxed in, unless it can be neatly clipped in place.
All previously varnished timber panelling is to be rubbed down, prepared and re-varnished using a good quality polyurethane varnish in accordance with the manufacturer's instructions.
2no Item Item Item
               3.7 Staircase (2nd Flr - 1st Flr)
3.7.1 The ceiling is to be rubbed down, prepared and decorated with 1no undercoat and 2no top coats Item of good quality paint.
3.7.2 The light fitting is to be removed and the new light fitting installed in a new position to fall in line 1no with the Building Regulations.
3.7.3 The walls are to be rubbed down, prepared and decorated with 1no undercoat and 2no top coats Item of good quality paint. Colours to be agreed with the client.
3.7.4 The windows are to be eased and adjusted and left operational. Item
3.7.5 The mechanisms to the windows are to be thoroughly cleaned to removed all paint residue and Item staining.
3.7.6 The windows are to be rubbed down, prepared and decorated with 1no undercoat and 2no top 2no coats of good quality gloss paint. Colour to be agreed with the client.
3.7.7 The cracked window pane is to be carefully removed and replaced with new to match the existing. 1no
3.7.8 The terrazzo finish to the cills are to be thoroughly cleaned. This may include honing, sealing and 2no polishing the cills to revitalise the finish.
3.7.9 The window surrounds are to be rubbed down, prepared and decorated in accordance with 2no manufacturer's recommendations.
3.7.10 The terrazzo finish to the treads, risers and upstands are to be thoroughly cleaned. This may Item include honing, sealing and polishing the steps to revitalise the finish.
3.7.11 The terrazzo finish to the surrounds up to the handrail is to be thoroughly cleaned. This may Item include honing, sealing and polishing the steps to revitalise the finish.
3.7.12 The timber handrails are to be removed, the fixing points made good and the handrails reinstated Item on completion.
3.7.13 Rub down, prepare and varnish the timber handrails with 2no coats of good quality polyurethane 3no varnish.
3.7.14 The previously varnished timber panelling surrounding the windows are to be rubbed down, 2no prepared and re-varnished using a good quality polyurethane varnish in accordance with the
manufacturer's instructions.
3.7.15 The terrazzo finish to the treads and risers is to be thoroughly cleaned. This may include honing, 13no sealing and polishing the steps to revitalise the finish.