Project Timeline






                                       2020                          2021                            2022                          2023


               Milestone         Apr  May  Jun  Jul  Aug  Sep  Oct  Nov  Dec  Jan  Feb  Mar  Apr  May  Jun  Jul  Aug  Sep  Oct  Nov  Dec  Jan  Feb  Mar  Apr  May  Jun  Jul  Aug  Sep  Oct  Nov  Dec  Jan  Feb  Mar  Apr  May  Jun  Jul  Aug  Sep




               Approvals        3 Months



               Design                    6 Months




               Construction                                         12 Months




               Leasing                                                                      12 Months




               Operations                                                                                                    12 Months









                                 Milestone          Permit       Construction Start    Leasing Start     Refinance         Sale
                                 Month               Dec               Jan                 Oct              Sep            Sep
                                 Year               2020               2021                2021            2023           2024