Project Timeline
2020 2021 2022 2023
Milestone Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep
Approvals 3 Months
Design 6 Months
Construction 12 Months
Leasing 12 Months
Operations 12 Months
Milestone Permit Construction Start Leasing Start Refinance Sale
Month Dec Jan Oct Sep Sep
Year 2020 2021 2021 2023 2024