Page 25 - CEL Utilities Brochure Nov 2020
P. 25

Key Features
                                                                                              ────
                                                                                    Design & implementation of
                                                                                 Pedestrian & Traffic Management
                                                                                              ────
                                                                                  Installation of 180m of 375mm
                                                                                  S & S concrete foul sewer pipe at
                                                                                       depths of 3m – 5.5m
                                                                                              ────
                                                                                  Installation of precast concrete
                                                                                 watertight manhole bases & rings
                                                                                              ────
                                                                                  Installation of precast concrete
                                                                                   kerbs & precast concrete kerb
                                                                                             edging
                                                                                              ────
                                                                                    Installation of new ducting
                                                                                 including new draw pit chambers
                                                                                       for MV & LV services
                                                                                              ────

                                                                                  Installation of a new gas main &
                                                                                    creation of 4 connections to
                                                                                          existing mains
                                                                                              ────
                                                                                  Installation of a new watermain
                                                                                   with valves, hydrants & thrust
                                                                                             blocks
                                                                                              ────
                                                                                 Reinstate of bituminous macadam
                                                                                     footpaths & carpark area
                                                                                              ────
                                                                                   Installation of road markings
                                                                                              ────
                                                                                   Landscaping including topsoil
                                                                                       covering & reseeding
                                                                                              ────



         UCD FOUL SEWER EXPANSION AND

         UTILITY WORKS 2015


         Client: University College Dublin
         Contract Value: €267k
         Location: University College Dublin, Belfield, Dublin 4.

         General Description
         The project was the installation of 180m of foul sewer on the live Belfield   CLONMEL ENTERPRISES LTD