Page 13 - CEL Utilities Brochure - 2020
P. 13

Key Features
                                                                                              ────
                                                                                  Site clearance of existing internal
                                                                                     road network RTE Campus
                                                                                              ────
                                                                                     Site clearance of existing
                                                                                    footpaths and cycletracks on
                                                                                          Stillorgan Road
                                                                                              ────
                                                                                   Construction of new drainage
                                                                                             network
                                                                                              ────
                                                                                  1100m² of new footpaths to DCC
                                                                                            standards
                                                                                              ────
                                                                                  200m² of off‐road cycle track to
                                                                                          DCC standards

                                                                                              ────
                                                                                  2400m² of full road construction
                                                                                              ────
                                                                                   Design and implementation of
                                                                                 traffic management on the N11 to
                                                                                  facilitate the instatement of the
                                                                                           new junction
                                                                                              ────
                                                                                  Construction of 55 no block‐built
                                                                                  gully chambers to DCC standards
                                                                                              ────
                                                                                   Construction of 20 no. pre‐cast
                                                                                   stormwater manholes ranging
                                                                                  between 1200mm and 1800mm
                                                                                            diameter
                                                                                              ────
                                                                                 Installation of 400m ACO drainage
                                                                                    kerbing, 405mm and 305mm
                                                                                              ────
         RTÉ NEW N11 JUNCTION                                                      Installation of 150m ACO road
                                                                                  drainage 300mm deep, including
                                                                                        several sump units
         Client: RTÉ Donnybrook
         Contract Value: Sensitive
         Location: Raidió Teilifís Éireann Dublin

         General Description
         This project was the construction of a new signalised junction and new road
         layout inside the RTE Campus.


                                                                                       CLONMEL ENTERPRISES LTD
                                                                                              Unit R,
                                                                                          M7 Business Park,
                                                                                             Newhall,
                                                                                               Naas,
                                                                                             Co. Kildare.
   8   9   10   11   12   13   14   15