FEATURE

                                                      THE COMING OF

                                                          Nigeria’s










                                               BUSIEST RAIL LINE











                                                                          By Aondohumba Agabi










              The 156.65km Lagos-Ibadan standard  The contractor, CCECC, is largely giving  move over 1 million commuters monthly.
              gauge rail facility might go down as one  excuses as to why it would fail. It blamed  An economist and financial analyst, Mr.
              of the most critical public infrastructure  the rain. It had blamed delayed payment  Bismarck Riwane who had visited the
              built by  the  President  Muhammadu  but that is no longer the case. In fact,  facility early this year had told journal-
              Buhari led government. It may also pass  based on the minister’s October visit to  ists that facility when completed has the
              the business and most profitable rail line  inspect  the  facility,  it  was  obvious,  the  capability of driving down inflationary
              when completed.                      penchant for the Chinese firm to import  pressure on Nigeria’s economy.
              This is largely due to the heavy traffic  most of the materials from china, even  “The project is quite impressive. It’s a mas-
              both in human and goods that is antici-  the ones that can be sourced locally,  sive project and it will have a multiplier
              pated will use the facility.         largely caused the delay.            effect on the economy when it’s finished.
              The facility that traverses three states –  Based on the last visit, none one of the  It will reduce logistics and distribution
              Lagos, Ogun and Oyo – is being procured  12 stations are ready, not even the minor  cost which is a major area of inflationary
              with a $1.5bn soft loan from China. The  four. Of course there is the challenge of  pressure in Nigeria” he said adding that
              FG also injected some N72bn into the  extending the line Iju to Ebutte Metta,  “anything that reduces inflation impacts
              project in counterpart funding.      through the heavy infrastructure of Lagos  the economy” he said.
              Although the line, a segment of the  and navigating through pipelines and all  He would also say “It’s the impact of the
              anticipated 2,733km Lagos-Kano double  that stand in the way.             investment rather than the Investment
              gauge line might be the most critical  A recent visit to the facility show that  itself that create jobs, reduce cost and
              stretch when completed.              over 75 percent or more of the tracks  improve productivity which is the major
              The Lagos-Ibadan rail line is a three  has  been  laid.  Mr.  Amaechi  is  pushing  concern in Nigeria” he noted.
              years old contract awarded to China Civil  for test run from Ebutte Metta to Ibadan  Mr. Amaechi had also spoken on about
              Engineering and Construction (CCECC)  by November 25th or at latest before  the potential impacts. He said the facility
              that terminates March 2020.  The com-  Christmas. The contractor is however only  is a part of the solution to the crisis of
              pletion date remains doubtful but the  assuring the test run would happen from  Lagos sea port.
              Minister of  Transportation Mr. Rotimi  Iju  to  Ibadan,  an  option  Amaechi  has  “The moment you fix the rail, the goods
              Amaechi has given marching orders to  refused.                            will transfer to the rail and the lock jam
              complete the project latest December  This facility when completed is anticipat-  will be over, especially the goods going
              2019. This is not the first deadline he would  ed to take off over 200 trailers off Lagos-  to Ibadan” he said.  “So the pressure is
              give.  He previously gave a  December  Ibadan road as people would move  more economic than political on people”
              2018 deadline. He would extend it to May  goods more on rail rather than road thus  he said.
              2019 and now December 2019.          elongated the life of the road and making  Nigerians are indeed excited about this
              However, there is nothing to suggest this  the roads safer and saner. It is also antici-  facility and can’t wait to see it operational.
              deadline would work.                 pated to employ over 1000 Nigerians and