PROJECT PROFILES
In mid-2023, Rosendin was awarded two projects at San
Francisco International Airport (SFO). Both design-build
projects will update the International Terminal Building
(ITB) by installing a photovoltaic (PV) array as part of the
roof replacement and a multi-phase project to modernize
the terminal building. These projects are part of the Airport
Development Plan 2016, which details the plan for long-
term development at SFO. This collection of projects will
enable SFO to accommodate up to 71.1 million annual
passengers within the capacity of the existing airfield.
The Rooftop PV project is in the preconstruction phase
and will add up to 1.4 MVA to the roof of the International
Terminal Building. Rosendin is the electrical contractor
San Fransisco providing design and preconstruction support for a
photovoltaic system of about 1440 KVA, including monitoring
and metering on the International Terminal Building.
International Airport The modernization of the International Terminal Building
is also in the preconstruction phase. Rosendin’s scope of
work includes electrical systems design and preconstruction
Terminal Building support for converting baggage claims three and 12 and BAA
and BAF immigration upgrades. The project will include a
new consolidated processing area, relocation of Customs and
Border Patrol offices, and new auto exit lanes for the ITB.