CORPORATE TENANT  SIZE                SCHEDULE                                      STATUS                                   TRANSACTION TYPE

 State Farm Regional HQ at CityLine  2,100,000 SF  42 Months               Complete: 9,000 Employees                        NNN Lease / Open Book


 Raytheon at CityLine  489,000 SF       15 Months                          Complete: 1,500 Employees                        NNN Lease / Open Book


 Toyota Motor North America HQ at Legacy West  2,100,000 SF  30 Months     Complete: 7,000 Employees                             At Risk Dev Fee

 Liberty Mutual Insurance at Legacy West  1,100,000 SF  26 Months          Complete: 5,500 Employees                        NNN Lease / Open Book


 JPMorgan Chase Regional HQ at Legacy West  1,500,000 SF  21 Months        Complete: 6,000 Employees                     At Risk Dev Fee / Land Owner

 FedEx Office HQ at Legacy West  265,000 SF  12 Months                     Complete: 1,100 Employees                        NNN Lease / Open Book

 KDC CORPORATE   State Farm Data Centers (2)  300,000 SF  16 Months         Complete: 100 Employees                                NNN Lease



 Frost Bank HQ  500,000 SF              24 Months                          Complete: 1,700 Employees                        NNN Lease / Open Book
 OFFICE DEVELOPMENT   Independent Financial  159,000 SF  12 Months          Complete: 400 Employees                              At Risk Dev Fee




 DURING THE PAST   Pioneer Natural Resources HQ  1,125,000 SF  25 Months   Complete: 2,500 Employees                        NNN Lease / Open Book

 Epic Phase I  250,000 SF               24 Months                          Complete: 2,200 Employees                             At Risk Dev Fee

 FIVE YEARS  Uber, Epic Phase II  500,000 SF  30 Months         Underway (2022 Completion): 3,000 Employees                      At Risk Dev Fee



 Credit Suisse  400,000 SF              15 Months                          Complete: 3,900 Employees                             At Risk Dev Fee

 State Farm at Park Center Regional HQ  1,750,000 SF  39 Months  Underway (2021 Completion): 9,000 Employees                  Fee Dev / Open Book


 Baylor Scott and White  300,000 SF     23 Months                          Complete: 1,500 Employees                             At Risk Dev Fee


 SRS Distribution  100,000 SF           14 Months                           Complete: 500 Employees                                NNN Lease

 Sammons Financial Group  217,000 SF    16 Months                           Complete: 700 Employees                              At Risk Dev Fee


 Raytheon McKinney  200,000 SF          14 Months                           Complete: 500 Employees                              At Risk Dev Fee


 TOTAL LAST 5 YEARS  13,355,000 SF  22 MONTHS AVG                              56,100 EMPLOYEES