2.5.10 the effective date" – signature date; 2.5.11 "the joint venture" – collectively the parties in
                   fulfilment of the object of the joint venture as contemplated in clause 4.3 below;

                   2.5.12 "know-how" – all confidential information relating to the intellectual property and its
                   exploitation as well as all other confidential information relating to the manufacture, use and sale of
                   the product, including, without limitation, technical information, manufacturing techniques and
                   designs, specifications, formulae, systems, processes, information concerning materials and
                   marketing and business information generally;

                   2.5.13 “nett profit” – the total amount (less VAT) payable to the joint venture to execute “the
                   works”, less the total cost of project

                   ; 2.5.14 "the parties” Gonlizar and Phatsimo Engineering;
                   2.5.15 "signature date" – the date on which this agreement is signed by the party signing last in
                   time;

                   2.5.16 “total cost of project” – the listed costs, which includes, but are not limited to cost of land (if
                   applicable), tax, VAT, material, finance costs, labour, machine hire, security and in general, all gross
                   costs to execute the “works”;
                   3. INTRODUCTION

                   3.1 Gonlizar is a developer of low cost housing projects (“the works”) and other building projects.
                   3.2 Phatsimo Engineering has engineering and marketing expertise in identifying and owns “the
                   works” to the joint venture.

                   3.3 The parties wish to establish a joint venture to identify and execute “the works” to their mutual
                   advantage within the territory.
                    4. JOINT VENTURE

                   4.1 The parties have agreed to form a joint venture as contemplated in this agreement

                   .4.2 The joint venture shall be deemed to have come into existence on the effective date upon
                   signing of this agreement and shall be for the completion of a 10 000 (Ten Thousand) units of phase
                   1 from the effective date, unless it is extended by the parties in writing, or terminated by
                   agreement, or by either of the parties as contemplated in clause 18 below.

                   4.3 The object of the joint venture is to identify for the execution of “the works” within the
                   Ekurhuleni – John Dube Village Ext 1.

                   4.4 The parties' contributions to the joint venture are as follows:

                   4.4.1 Gonlizar will execute “the works”, which the execution and delivery of the subsidized 10 253
                   units for neighbourhood1 as per subsidy agreement attached; and subsequent units thereafter as
                   per main contract between Paradigm and John Dube Development Company , as part of the joint
                   venture, and the resources necessary to execute “the works”;

                   4.4.1.1 The value of the works to be executed is R 6, 000,000,000 (Six Billion) as per subsidy
                   agreement attached.