Page 2 - How do I Update the Project Activity Closed Status
P. 2

Project Activity Status Dates


        1.  Enter the Project.

        2.  Click Search.

        3.  Select the correct project & activity combination (not shown).









                                      2







                                                                                     1









               1.  Update the New Effective Date.

               2.  Click Change Close Date.
















                                                               1











               1.  Validate the Effective Date is new closed date and Final Date is + 30 days.









                                                                                                             Page 2 of 4

        Emory Confidential and Proprietary           Last Revised on 6/22/2017                  Return to Table of Contents
   1   2   3   4