Page 8 - How do I Add an Activity
P. 8

Add an Activity


        1.  Click View All to display all Activities for the Project where the Activity was added.











                   2










        2.  Click Change to enter the F&A Information.










                   2                           3

















                                               4                                             5


                6


        3.  Enter Facilities Admin Rate. Updates Eff Date and FA Rates.
        4.  Update FA Base as needed.
        5.  Update FA Rate % as needed.
        6.  Click Save.

        Close browser tab and refresh.
            D. Create Statuses via Date Change Page.

        Use job aid How do I Change Dates on an Award? Using same dates for all Projects and Activities updated.




                                                                                                             Page 8 of 9
         Emory Confidential and Proprietary           Last Revised on 2/19/2018                 Return to Table of Contents
   3   4   5   6   7   8   9