Page 110 - GM Booklet Dec 2022 demo
P. 110
14. Greenery improvement measures
Swachhta Pledge at DLS/MLY
As part of Swatchhta Pakhwara, a pledge for “initiating the quest for cleanliness and devoting
100 hours towards cleanliness” was administered by all officers, supervisors and shed staff
on date 16-09-2022 and all the shed staff have participated and cleaned the shed premises
at DLS/MLY
15. PROGRESS OF SANCTIONED WORKS:
Augmentation of DEMU Facilities:
Augmentation of MEMU/DEMU Car shed for holding 16 MEMU/DEMU
rakes at DLS/MLY.
Pink Book No.637 of 2022-23, PH:4200
Original
sanction Detailed
cost in Estimate Present status.
d Cost
Rs.
9.61 12.83 Civil works:
Crores Crores Construction of OHE/TRD/SC material shed, approaching road with RPF post
has been completed.
Stabling line & cross over track completed.
Shunting neck line works completed.
Construction of Admin Building & construction of pit line under Progress & is
under final stage.
Electrical works:
Lighting to OHE/TRD/SC Material shed, RPF Post and Shed approaching road
are completed.
Lighting to Admin Building and DEMU pit line is under progress.
2 No.s of 10 KVA Solar plant to be installed in new Admin building.
Mechanical works (M&P items)
Welding plants Qty:2 Nos received & commissioned on 18-10-2021
NS Indent for Procurement of Air Compressors Qty:02 Nos, PO released on
Colt Equipment, Haryana. Material expected in the month of January 2023.
Funds certification for procurement of Office furniture has been obtained. SPC
has been nominated and NS indents have been prepared and submitted to
Sr.DFM/HYB for vetting.
S&T.
Shifting of the work S&T exchange to the existing admin building is completed
and other works i.e., PA system and LAN works to be started in Admin building.
108