Page 128 - GM Booklet Dec 2022 demo
P. 128
1. Progress of MOU items
% of
Boards
Sl Unit of Progress Progress
No Key Performance Indicator Measurement Target 2022-23 over target
2022-23
2022-23
1 Progress of Track Renewals CTR Units 40.18 37.8225 94.13 %
2 Deep Screening of Turnouts Nos 50 24 48.00 %
3 Deep Screening of Plain Track Kms 50 32.790 65.58 %
Removal / Relaxation of
4 Nos - 3 3
Permanent Speed Restrictions
Elimination of Manned of Level
5 Nos 10 8 80.00 %
Crossing Gates
2. Performance of track renewal works:
Progress
S. Target Progress Target 2022-23
No Item Unit 2020-21 2021-22 2022-23 (Upto
Nov‟22)
CTR
1 Track Renewal 23.93 13.42 73.38 37.8225
Units
a)Through Rail Renewal (P)
TRR(P) Tkm 30 13.13 100 46.275
b)Through Sleepers Renewal (P)
TSR(P) Tkm 7 8.9 35 23.995
c)Through Rail Renewal (S) Tkm 10 3.95 11 4.610
TRR(S)
d)Through Sleepers Renewal (S)
TSR(S) Tkm 0.860 0.960 0.764 0.765
2 Through Fitting Renewal - TFR Tkm 168.3 100.785 200 39.500
Through Fitting Renewal on
3 Nos 10 0 0.7 0
Turnouts – TFR-T/O
4 Through Weld Renewal - TWR Tkm 20 3.62 29.227 1.263
Through Formation Treatment -
5 Tkm 80 70.98 50 27.170
TFTR
6 Deep Screening of Plain Track Kms 50 66 50 24
7 Deep screening of Points Nos 50 - 131 41
126