Page 5 - GM Booklet Dec 2022 demo
P. 5
COMMISSIONING OF NEW BRANCH LINE (BG)
S. No Section KMs Date commissioned
01 Gadwal - Raichur 57.16 12.10.2013.
CRS inspection done on 27.10.2016 and
02 Devarkadra – Jaklair 28.26
section taken over.
CRS Inspection done on 05.06.2020 and
03 Jaklair - Makthal 11.47
section to be taken over by Open line.
CRS inspection done on 27.03.2022 and
04 Makthal - Magnur 13.305
section to be taken over by Open line.
CRS Inspection done on 19.06.2020 and
05 Manoharabad - Gajwel 31.07
section to be taken over by Open line.
CRS Inspection done on 28.02.2022 and
06 Gajwel - Kodakandla 11.529
section to be taken over by Open line.
CRS Inspection done on 26.03.2020 and
07 Akannapet - Medak 17.338
section to be taken over by Open line.
COMMISSIONING OF RAILWAY ELECTRIFICATION
S. No Section RKMs Date commissioned
1 Secunderabad - Falaknuma 16.021 14.02.2004
2 Secunderabad – Moula-ali 11.617 10.10.2010
3 Malkajgiri – Bolarum 12.69 14.03.2018
4 Bolarum – Medchal 14.95 18.07.2019
5 Medchal – Manoharabad 13.078 07.10.2020
6 Falaknuma – Umdanagar 13.695 26.03.2021
7 Umdanagar – Gollapalli 60.733 25.08.2021
8 Timmapur / CMPTL Sdg 0.557 22.09.2021
9 Gadwal – Raichur 57.7 30.08.2021
10 Nizamabad Yard 2.23 24.02.2022
11 Kurnool City – Dhone 54.3 17.03.2022
12 Gollapalli – Mahabubnagar 25.549 31.03.2022
13 Nizamabad – Bodhan 25.85 31.03.2022
14 Manoharabad - Kamareddi 66.37 27.10.2022
15 Mahabubnagar- Gadwal 72.70 27.11.2022
448.04
3