GAUGE CONVERSION / DOUBLING


               S.
              No                          Section                            KMs      Date commissioned
               1    Secunderabad-Falaknuma  (UP) line                          14          02.06.1993
               2    Secunderabad-Bolarum  (UP line)                            14          10.06.1993
               3    Secunderabad-Falaknuma  (DN line)                          14          24.06.1993
               4    Falaknuma  - Mahbubnagar                                   99          21.08.1993
               5    Mahbubnagar  - Dhone                                      184          31.03.1998
               6    Mudkhed - Dharmabad                                        48          02.06.2002
                    Dharmabad - Nizamabad
               7                                                               60          03.10.2002
                    (including  Jankampet - Bodhan)
               8    Bolarum - Manoharabad                                      27          14.02.2004
               9    Manoharabad - Nizamabad                                   120          07.02.2005
              10  Secunderabad-Bolarum  (DN line)                              14          10.05.2006
              11  Bolarum - Medchal (DN line) (Double line)                    14          18.03.2019
              12  Shadnagar – Gollapalli (DN Line) (Double line)               30          16.09.2020
              13  Falaknuma  – Umdanagar (DN Line) (Double Line)               14          26.03.2021
              14  Umdanagar – Shadnagar (DN Line) (Double Line)                30          21.07.2021
                                                                              682

                        COMMISSIONING  OF NEW BRANCH LINE (BG)





           S. No                                       KMs                   Date commissioned
                              Section
            01           Gadwal - Raichur              57.16                       12.10.2013

                                                                CRS inspection done on 27.10.2016 and
            02         Devarkadra – Jaklair            28.26
                                                                section taken over.
                                                                CRS Inspection done on 05.06.2020 and
            03           Jaklair - Makthal             11.47
                                                                section to be taken over by Open line.

                                                                CRS Inspection done on 19.06.2020 and
            04        Manoharabad - Gajwel             31.07
                                                                section to be taken over by Open line.



                                    TOURIST AND PILGRIM  CENTRES


                   Hyderabad,  the  capital  of  Telangana,  is  an  exciting  holiday  destination.    A  blend  of
            heritage  and  modernity,  it  has  a  wide  ranging  choices  for  sightseeing  and  facilities  for
            leisure  &  pleasure:  parks,  lakes,  temples,  museums,  heritage  monuments,  entertainment
            and shopping centers.

            Charminar:  Built  when  the  city  was  born,  the
            Charminar‟s  four  minarets  rise  to  a  height  of  180
            feet with circular staircases within.  The edifice is an
            architectural  wonder  and  a  monument  worth
            seeing.  Charminar is illuminated  in the evenings.

                                                            3
   1   2   3   4   5   6   7   8   9   10