Page 45 - Sample _ STARTER KIT SHIFT ENGINEER 2017v
P. 45

STARTER KIT | Shift Engineer



                        d.  Inspect and check floor for cracks, tile
                           grouting and flooring elevation.
                        e.  Inspect and check all plumbing details and
                           materials (Water Closet, Faucet,
                           Sink/Lavatory, Bidet, Floor Drain, Water
                           Leaks, Ceiling Leaks and P-Trap).
                        f.  Inspect and check all electrical details and
                           materials (Lighting Appearance, Power
                           Outlets, Smoke Detectors and Circuit
                           Breakers).
                        g.  Inspect and check all carpentry details and
                           materials (Tables, Chairs, Cabinets, Drawers,
                           Shelves, Doors, Door Stopper and Door
                           Closer).
                        h.  Inspect and check ventilation details and
                           materials (Air Conditioning Units, Ceiling Fan
                           and Exhaust Fan).

                    3.  Inspect and check WIFI and internet connectivity.


               Task 13:  Evaluate and assess job order requests
                          OPERATING PROCEDURES                                 STANDARD(s)

                    1.  Respond immediately to equipment breakdown.

                    2.  Evaluate status of the equipment and make
                        appropriate resolutions and recommendations.

                    3.  Assign repair works to maintenance personnel
                        depending on the priority list of job orders.

                    4.  Follow-up status of pending Job Order Requests to
                        the assigned personnel.


               Task 14:  Summarize reports during the shift
                          OPERATING PROCEDURES                                 STANDARD(s)

                 Prior to logging out after shift reports must be updated and
                 summarize including but not limited to:
                    1.  Consumption Reports (Electricity & Water)

                    2.  KPI (Daily Accomplishments of Painter, Laborer,
                       Carpenter, Plumber and Handyman)

                    3.  Prepare turnover report of ongoing projects and
                       pending Job Orders







                                                             40
   40   41   42   43   44   45   46   47   48   49   50