Page 8 - MIN ECEM 3 JULY 2017
P. 8
E PROYECTO LO TUMA LUGAR DEN 2 FASE; FASE 1 LO CUMINSA DIALUNA,
3 DI JULI Y LO REKERI PA AEROPUERTO SERA POSICIONNAN DI PARKEER 2
Y 3 PA UN PERIODO DI 6 SIMAN. ORA CU FASE 1 KEDA CLA, FASE 2 LO
CUMINSA, UNDA CU GATE 3 LO BOLBE DEN SERVICIO MIENTRAS CU GATE
1 Y 2 LO WORDO SERA PA UN PERIODO DI 4 LUNA, CU FECHA PA KEDA CLA
DIA 14 DI DECEMBER, 2017. E SERAMENTO DI E GATENAN LO CAUSA UN
CANTIDAD DI RETO PA E OPERACIONNAN DIARIO PA AEROPUERTO, PERO
VARIOS PROCESO PA POR TRAHA ROND DI E PROYECTO LO WORDO
IMPLEMENTA PA ASINA MINIMALISA E IMPACTO RIBA E PASAHERO Y
OPERACIONNAN DI AVION.
MANAGER DI AIRPORT DEVELOPMENT MONTHY CROES TA HOPI
OPTIMISTA RIBA E PROYECTO: “E PROYECTO AKI A WORDO BON PLANIA Y
NOS TA ANCIOSO PA CUMINSA CU E EHECUCION. NUNCA LO TIN UN
MOMENTO IDEAL PA REDUCI CAPACIDAD NA UN AEROPUERTO CU TA
OPERA CU VOLUMENNAN PEAK, PERO E PROYECTO AKI TA CRITICO PA
POR SIGUI MANTENE E FACILIDADNAN DI AEROPUERTO, Y ORA E KEDA
COMPLETA, LO DUNA E EKIPO DI OPERATIONS MAS FLEXIBILIDAD NA
MOMENTO DI TRAHA E SCHEDULE Y NA MES MOMENTO TA RENOBA
INFRASTRUCTURA CU A BIRA BIEU, CU TA DI SUMA IMPORTANCIA PA UN
AEROPUERTO MODERNO. NOS ENFOKE LO TA PA SIGURA CU E PROYECTO
WORDO ENTREGA NA TEMPO, PROME CU E TEMPORADA PEAK DI WINTER”