                  Grants to Facilitate the Siting of Interstate Electricity Transmission Lines



               Federal Agency: Department of Energy
               Bureau or Office: Grid Deployment Office



               IRA Statutory Location: 50152

               Program Description: To facilitate siting of transmission projects by providing grants to siting
               authorities to expedite the siting and permitting process and providing grants for economic
               development activities in communities that may be affected by a transmission project.


               Funding Amount: $760,000,000

               Period of Availability: To remain available through September 30, 2029, provided that the
               Secretary shall not enter into any grant agreement pursuant to this section that could result in any
               outlays after September 30, 2031.

               Funding Mechanism: Grants


               New or Existing Program: New

               Eligible Recipients: Transmission siting authority, or other state, local, or Tribal governmental
               entity

               Tribal Eligibility: Yes

               Eligible Uses: (1) Grants to siting authorities for analysis, examination of alternative siting
               corridors, participation in regulatory proceedings in other jurisdictions related to a transmission
               project, or other measures that reduce the time to site and permit a transmission project. A siting
               authority must agree, in writing, to reach a final siting or permitting decision not later than 2
               years after the date on which a grant is provided. (2) Grants for economic development activities
               for communities that may be affected by the construction and operation of transmission projects.
               The Secretary may only disburse grant funds for economic development activities to (a) a siting
               authority upon approval by the siting authority of the transmission project; and (b) to any other
               state, local, or Tribal governmental entity upon commencement of construction of the
               transmission project.

               Cost Share Requirements: Federal cost share shall not exceed 50% for grants to siting
               authorities for participation in regulatory proceedings in other jurisdictions and at FERC. No
               specified cost share requirement for other grants under this provision.


               Formula Funding: No

               SAM.gov Assistance Listing: TBD



                                    B U IL D IN G   A   C L E A N   E N E R G Y   E C O N O MY             37
                                   G U ID E B O O K   |   J AN UARY   20 2 3   |   VE RS I O N   2
   37   38   39   40   41   42   43   44   45   46   47