Page 9 - Railways
P. 9

www.moniterra.engineering                                                                  RAILWAYS




          with +/- 3mm accuracy and the installation was carried out
          by the above machine with the help of workers.
          - Final Adjustment, where now the detailed tracing was
          carried out with +/-0.9mm accuracy, manually and with
          the appropriate tools for the micro-corrections.
          - Inspection-acceptance (As Built) correspondingly, as
          with  the  rails  on  the  ground.  Here,  the  identification  of
          any theoretical—constructed track deviations was more
          frequent, since it could not exceed 1 km and the concreting
          of the mounting of the rails intervened with the subsequent
          micro-movements.


      •   3.5km railway tracks on a slab inside the “Monastiraki –
          Attiki” tunnel.
          - The same methodology was followed here as with
          the  foundation  rails  before,  during  the  rough  and  final
          adjustment and the inspection-acceptance phases.
          - Their difference, as regards the methodology, with those
          outside the tunnel, pertains to an interim stage between
          rough and final adjustment. After rough adjustment, and
          certainly before the final adjustment, it was necessary to
          inspect the tunnel’s clearance in real time.
          Due to the small gauge of the tunnel, in width and height,
          and therefore the narrow space, this was done in order
          to determine with certainty and precision any interference
          by any elements (supports, walls, cables, cable shelves,
          electromechanical  boxes,  signals,  signs,  etc)  within  the
          clearance that was provided for and should exist for the
          correct construction of the project.
          This inspection was carried out at sections of the line each
          time, with the most advanced GRP 5000 control system.


      Monitoring  of  micro-movements  at  the  section  of  the
      “Monastiraki-Omonoia” railway network.
             The 850m-long (total length 1465 m) section of the ISAP
      line between Monastiraki – Omonoia, is located inside the old
      660m tunnel, which was constructed in 1893. Thus, due to
      the age of the tunnel, one of the project’s objectives was to
      support it, and therefore to take preventive measures during
      the progress of the works inside it.
             Our surveying support played an instrumental role in this
      part, and pertained to monitoring the micro-movements inside
      and outside the tunnel, i.e. underground and above ground.
      •   Underground:
          Monitoring micro-movements included any convergence
      presented by the tunnel walls. Before measurements started,
      permanent controls had to be installed, which were targets
      installed on tie rods embedded in the walls. After installation
      and before the start of the works, “zero” measurements of the
      controls were taken, in order to accurately observe their initial
      position. Then, and simultaneously with the start of the works,
      measurements were taken on a daily basis and their results
      were sent directly to the construction company.



                                                                                                            9
   4   5   6   7   8   9   10   11   12