TIMELINE – FACTORS
Oct 2010 – A six-year plan agreed.
Six-year expansion plan outline
• 2013 - £249k for packaging projects
• 2013 - £5.6m to deliver a self-contained, lean facility with
new Rovema lines, Tablet Presses, Blender and IBC
Charging, fully operational 2014.
• 2013 / 2014 – £1.45m for major works - old packing hall for
fit out 2014.
• 2014 / 2015 - £2.5m to fit out old packing hall.
• Relocate presses / blenders into new area ready for
expansion in 2015 of lines 7,8 &9
• 2014 / 2015 - £2.1m over 12 months for to increase capacity
in SF2
Total Development Budget Costs
£12Million!