Page 20 - Doug_Martin_Construction_Book
P. 20
Q. What documentation does LMCU need prior to the first construction
disbursement after closing?
□ A copy of the Building Permit
□ Completed and signed General Contractor’s Inspection Request
and Payment Requisition Form
□ Foundation survey if slab is poured
□ Proof of Builders Risk (if not received at closing)
□ Construction Progress Inspection (ordered by LMCU’s construction
loan administrator)
□ Title Insurance Endorsement (ordered by LMCU’s construction
loan administrator)
□ Borrower’s Authorization
Q. What documentation is needed for interim draws?
□ Completed and signed General Contractor’s Inspection Request
and Payment
□ Lien waivers from the previous draw
□ Title Insurance Endorsement
□ Construction Progress Inspection
□ Labor costs paid when work is complete
□ Payments made for materials on site
Q. What documentation is required prior to the final disbursement?
□ Completed and signed General Contractor’s Inspection Request
and Payment
□ Contractor’s Final Payment Affidavit
□ Lien waivers from the previous draw
□ Certificate of Occupancy
□ Final Survey (when applicable)