Page 20 - Lisa_Kreza_Windridge_Estates_Lombardo_Homes_Construction_Book
P. 20
Q. What documentation does LMCU need prior to the first construction
disbursement after closing?
□ A copy of the Building Permit
□ Signed, notarized builder’s sworn statement
□ Foundation survey
□ Proof of Builders Risk (if not received at closing)
□ Construction Progress Inspection (ordered by LMCU’s construction
loan administrator)
□ Title Insurance Endorsement (ordered by LMCU’s construction
loan administrator)
□ Borrower’s Authorization
Q. What documentation is needed for interim draws?
□ Signed, notarized Builder’s Sworn Statement
□ Lien waivers from the previous draw
□ Title Insurance Endorsement
□ Construction Progress Inspection
□ Labor costs paid when work is complete
□ Payments made for materials on site
Q. What documentation is required prior to the final disbursement?
□ Final signed notarized Builder’s Sworn Statement
□ Lien waivers from the previous draw
□ Certificate of Occupancy
□ Final Construction Inspection
□ Final Title Endorsement
□ 100% complete statement signed by you
□ Insurance and tax information including a paid Home Owners
Insurance Policy