KALSEL BABUSSALAM BERGERAK UNTUK BANUA MAJU
Selain sumberdaya potensi bijih besi, Kabupaten Kotabaru In addition to potential iron ore resources, Kotabaru Regency,
khususnya Pulau Laut dan Pulau Sebuku yang berada di especially Laut Island and Sebuku Island, which are located in
tengah-tengah perairan Indonesia dan berdampingan dengan the middle of Indonesian waters and adjacent to the Makassar
Selat Makassar juga sangat ideal untuk industri smelter; Strait, is also ideal for the smelter industry, with advantages
dengan keuntungan pada biaya transportasi bahan baku in the transportation costs of raw materials and bulk products
dan produk yang bersifat bulk dalam jumlah besar. Ada dua in large quantities. There are two prospective locations for
lokasi yang prospektif sebagai lokasi pabrik smelter, yaitu smelter plants, namely Sebuku Island and Mekar Putih SEZ
Pulau Sebuku dan KEK Mekar Putih (sedang dalam proses (currently being proposed by South Kalimantan Province).
pengusulan oleh Provinsi Kalimantan Selatan).
Rencana lokasi smelter di KEK Mekar Putih berjarak ± 95 The planned location of the smelter in Mekar Putih SEZ is ±
km dari sumber daya bijih besi utama di Pulau Sebuku, 95 km from the main iron ore resource on Sebuku Island,
yang dapat ditempuh melalui jalur perairan. Desain smelter which can be reached by waterway. The smelter design is
berupa fasilitas produksi baja kasar dengan proses BF-BOF a crude steel production facility with BF-BOF (Blast Furnace
(Blast Furnace Basic Oxygon Furnace), Laddle Furnace dan CCM Basic Oxygon Furnace), Laddle Furnace and CCM (Continuous
(Continuous Casting Machine) dengan kapasitas produksi Casting Machine) processes with a production capacity of
600 ribu ton per tahun. Bahan baku utama adalah bijih besi 600 thousand tons per year. The main raw materials are iron
134 dengan kadar 62%, kokas, batu bara dan kapur. Kebutuhan ore with a grade of 62%, coke, coal and lime. The electrical
daya listrik untuk membangun pabrik smelter di Pulau Sebuku power required to build the smelter plant on Sebuku Island is
adalah 205,449 MVA. 205.449 MVA.
sumber: Kementerian Investasi/Badan Koordinasi Penanaman Modal (BKPM) / Source: Ministry of Investment/Investment Coordinating