MOCKDRILLS





      MOCK DRILL AT FGD RIHAND PROJECT


       Emergency for which mock-drill is conduct: Manual Evacuation
       Type of mock-drill: Practice Drill
        Overall response time: 40 mnts



                     Good points of mock drill                           Observed shortfall in mock drill

         HSE immediately call to ambulance (First Aider) from
        the location. Responsible person with the site in charge        The Victim was not taken to a safe place
       picked up the phone and reached the location. First Aider          on time due to no proper safe access.
           check pulse rate by oximeter & Dressing, wound &
            secured the pad with roller bandage at location


            Corrective actions in related to observed
          shortfall in mock drill, Area of improvement               Responsibility                Target Date

        Safe access to be provided for inside chimney raft.            Bikash Patel                23/08/2021