Page 36 - Cost Accounting - Ready Reckoner
P. 36
33
1. Material Cost Variance (MCV)
Material Cost Variance
(MCV)
1-2
SPSQ - APAQ
Material Price Variance Material Usage Variance
(MUV) (MUV)
3 - 2 1 - 3
(SP - AP)AQ (SQ - AQ)SP
Material Mix Variance Material Yield Variance
(MMV) (MYV)
4 - 3 1 - 4
(RSQ - AQ)SP (SQ - RSQ)SP
SQ = Standard Quantity for Actual Production
AQ = Actual Quantity
SP = Standard Price
RSQ = Revised Standard Quantity (Actual Quantity in Standard mix)
AP = Actual Price
RSQ arises when there is more than one material used for production
1 2 3 4
SPSQ APAQ AQSP RSQSP
MCV = MPV + MUV
MUV = MMV + MYV