Information on River Road From Caroline County Government
Caroline County residents: We hear your concerns and share allowing additional construction to begin on July 29.
your frustration regarding the closure of River Road. The • This project is anticipated to be completed in late August,
decision to initiate the River Road Culvert Replacement was barring no unforeseen circumstances.
a proactive measure aimed at averting a potential road failure • We will provide regular updates to keep you informed of
that could have had widespread impacts across our county. progress and any adjustments to the timeline.
Here’s an overview of why the road was closed in June and Please understand that a temporary road closure of two to
our current progress, as of July 25, 2024: three months is necessary to ensure the long-term safety
Reason for Closure: and stability of River Road. This proactive measure prevents
• The decision to close River Road in June was driven by the potential road washouts and ensures that the project is
urgent need to prevent a potential major road failure. completed efficiently and effectively. We appreciate your
• The culvert under the road had deteriorated significantly, cooperation in making this essential improvement for the
posing a safety risk to motorists and threatening to worsen benefit of our entire community.
with time.
• Delaying the closure would have resulted in increased costs
and longer disruptions to traffic.
Current Status: Janet Dove, stylist
• Underground utility relocation has been in progress, with
one utility awaiting final clearance by July 26. Although
you can’t see “shovels in the ground”, several updates have 920 Gay St., Denton
occurred with many nighttime operations to finalize utility 410-310-4586
switchovers. For all of which, closure was needed. Appointments ONLY!
• This project involves replacing the existing pipes with a
more durable box culvert and raising the flood-prone section Please call to schedule
of the road by 1 foot. CUTS • COLOR • PERMS • HIGHLIGHTS
Environmental Considerations:
• Construction timelines are governed by state regulations
to protect sensitive habitats, such as fish spawning season.
Meaning, this is the approved timeline when we are allowed
to repair our county road. 13699 Greensboro Rd.
•We’ve worked to schedule construction to minimize Greensboro, MD 21639
environmental impact while ensuring safety and efficiency. 410-482-6897
Communication and Coordination: greaterimpactmd.com
• We have continued to collaborate closely with all our
partners, including emergency services, the Caroline County Saturday: 6 PM
Sheriff’s Office, local volunteer fire companies, and the Board Sunday: 11 AM
of Education, ensuring seamless communication throughout
this process to manage any potential disruptions during
construction.
Impacting Caroline County and beyond
Timeline:
with the love of Christ for eternal gain!
• Final utility relocation clearance is expected by July 26,
BINGO
CALLER
Looking for something to do
on Tuesday evenings?
Call Bingo at the Caroline Post!!
Up to a maximum of 4 hours a week, paid bi-weekly.
Starting fee of $50.00 per Bingo night.
This is a paid position subject to standard payroll taxes.
Contact the Legion at 410-479-2708 or Legion29@outlook.com
41