Page 6 - GREEN 2 RESIDENCES
P. 6

PROJECT DETAILS








                                                                                               Land Area                    1.6174 ha


                                                                                               No. of Towers                3 Towers


                                                                                               No. of Floors                19 storeys (excluding B1)



                                                                                               No. of Units                 3,254 (total for all towers)


                                                                                               No. of Parking               ±487 (to be shared by all towers)


                                                                                               Retail                       Ground Floor



                                                                                                                             nd
                                                                                               Amenity Floor                2 Floor (shared by all towers)

                                                                                               Launching Date               Tower 1 : August 2017

                                                                                                                            Tower 2 : August 2018

                                                                                                                            Tower 3 : February 2019


                                                                                               Turnover Date                Tower 1 : Ready for Occupancy

                                                                                                                            Tower 2 : December 31, 2022

                                                                                                                            Tower 3 : December 31, 2023


                                                                                                                                                              Image from Google
                         For training purposes only. This material may be subject to change and not for reproduction and distribution without prior consent of developer.
   1   2   3   4   5   6   7   8   9   10   11