Page 524 - National Electrical Price Guide
P. 524

05-22-19
      280-2
                                     HOLE PUNCHING - For Enclosures, Gutters, Panels & Switchboards

                                                                Average        Suggested   LABOR   HOURS
                                      Description        Cost     Resale      (0-6')   (6-10')  (10-15')  (15-20')
                               1/2"                       0.00        0.00     0.30     0.38     0.45     0.53
                               3/4"                       0.00        0.00     0.30     0.38     0.45     0.53
                               1"                         0.00        0.00     0.30     0.38     0.45     0.53
                               1-1/4"                     0.00        0.00     0.40     0.50     0.60     0.70
                               1-1/2"                     0.00        0.00     0.40     0.50     0.60     0.70
                               2"                         0.00        0.00     0.40     0.50     0.60     0.70
                               2-1/2"                     0.00        0.00     0.60     0.75     0.90     1.05
                               3"                         0.00        0.00     0.60     0.75     0.90     1.05
                               3-1/2"                     0.00        0.00     0.60     0.75     0.90     1.05
                               4"                         0.00        0.00     0.80     1.00     1.20     1.40
                               5"                         0.00        0.00     0.80     1.00     1.20     1.40
                               6"                         0.00        0.00     0.80     1.00     1.20     1.40


                                                              FIRE PROOFING

                                                                Average        Suggested   LABOR   HOURS
                                      Description        Cost     Resale     (0-6')   (6-10')  (10-15')  (15-20')

                               1/2"                    1.44         3.60       0.30     0.38     0.45     0.53
                               3/4"                    1.44         3.60       0.30     0.38     0.45     0.53
                               1"                      1.44         3.60       0.30     0.38     0.45     0.53
                               1-1/4"                  2.16         5.40       0.40     0.50     0.60     0.70
                               1-1/2"                  2.16         5.40       0.40     0.50     0.60     0.70
                               2"                      2.16         5.40       0.40     0.50     0.60     0.70
                               2-1/2"                  3.96         9.90       0.50     0.63     0.75     0.88
                               3"                      3.96         9.90       0.50     0.63     0.75     0.88
                               3-1/2"                  4.92        12.30       0.70     0.88     1.05     1.23
                               4"                      4.92        12.30       0.70     0.88     1.05     1.23








































                                         MATERIAL PRICES AND LABOR UNITS FOR FIREPROOFING ARE PER FOOT
                                                 LABOR UNITS FOR HOLE PUNCHING ARE PER EACH
      NPG                       AVERAGE COST COLUMN IS A NATIONAL AVERAGE AND SHOULD BE VERIFIED FOR YOUR AREA
      24-12                              COPYRIGHT © 1996-2019 by ELECTRICAL RESOURCES, INC.