Page 53 - National Electrical Price Guide
P. 53
08-27-19
10-59
O-Z/GEDNEY THREE PIECE UNIONS
Average Suggested LABOR HOURS
Description Cat. No. Cost Resale (0-6’) (6-10’) (10-15’) (15-20’)
1/2” 4-50 1.46 5.98 0.15 0.19 0.23 0.26
3/4” 4-75 4.29 7.68 0.17 0.21 0.26 0.30
1” 4-100 2.31 13.94 0.22 0.28 0.33 0.39
1-1/4” 4-125 7.96 28.03 0.25 0.31 0.38 0.44
1-1/2” 4-150 10.01 35.45 0.30 0.38 0.45 0.53
2” 4-200 16.30 70.91 0.40 0.50 0.60 0.70
2-1/2” 4-250 29.68 163.21 0.50 0.63 0.75 0.88
3” 4-300 45.12 248.08 0.65 0.81 0.98 1.14
3-1/2” 4-350 46.03 399.47 0.90 1.13 1.35 1.57
4” 4-400 87.95 437.20 1.20 1.50 1.80 2.10
5” 4-500 242.20 1,030.55 1.40 1.75 2.10 2.45
6” 4-600 322.73 1,373.32 1.60 2.00 2.40 2.80
Comparative Three Piece Unions
Description Appleton Raco Sepco T & B
1/2” EC-50 1502 1022 675
3/4” EC-75 1503 1023 676
1” EC-100 1504 1024 677
1-1/4” EC-125 1505 1025 678
1-1/2” EC-150 1506 1026 679
2” EC-200 1508 1027 680-TB
2-1/2” EC-250 1510 1028 681
3” EC-300 1512 1029 682
3-1/2” EC-350 1514 1030 683
4” EC-400 1516 1031 684
5” EC-500 1520 1005 686
6” EC-600 1524 1006 687
O-Z/GEDNEY SPLIT COUPLINGS
Average Suggested LABOR HOURS
Description Cat. No. Cost Resale (0-6’) (6-10’) (10-15’) (15-20’)
1/2” SSP-50 2.85 10.64 0.15 0.19 0.23 0.26
3/4” SSP-75 3.66 13.34 0.20 0.25 0.30 0.35
1” SSP-100 5.08 26.01 0.22 0.28 0.33 0.39
1-1/4” SSP-125 9.31 33.64 0.25 0.31 0.38 0.44
1-1/2” SSP-150 11.71 42.27 0.30 0.38 0.45 0.53
2” SSP-200 23.57 85.21 0.35 0.44 0.53 0.61
2-1/2” SSP-250 47.10 180.14 0.45 0.56 0.67 0.79
3” SSP-300 71.51 273.63 0.60 0.75 0.90 1.05
3-1/2” SSP-350 115.10 440.09 0.80 1.00 1.20 1.40
4” SSP-400 135.38 517.93 1.00 1.25 1.50 1.75
5” SSP-500 233.81 895.85 1.30 1.63 1.95 2.28
6” SSP-600 311.74 1,194.41 1.65 2.06 2.48 2.89
Comparative Split Couplings
Description Appleton Crouse-Hinds
1/2” SCC-50 TCC1
3/4” SCC-75 TCC2
1” SCC-100 TCC3
1-1/4” SCC-125 TCC4
1-1/2” SCC-150 TCC5
2” SCC-200 TCC6
2-1/2” SCC-250 TCC7
3” SCC-300 TCC8
3-1/2” SCC-350 TCC9
4” SCC-400 TCC10
5” - TCC12
6” - TCC14
MATERIAL PRICES AND LABOR UNITS ARE PER EACH
NPG/NSG AVERAGE COST COLUMN IS A NATIONAL AVERAGE AND SHOULD BE VERIFIED FOR YOUR AREA
1-21 COPYRIGHT © 1996-2019 by ELECTRICAL RESOURCES, INC.