PROJECT SUPERVISION
Calculating Foreman Supervision Hours
SIMPLE PROJECTS
Type Foreman Average Man Loading Labor Factor
Working 2 Men .125
Working 4 Men .250
Working 6 Men .375
Working 8 Men .500
Working 10 Men .625
Working 12 Men .750
Non-Working 16 Men 1.000
COMPLEX PROJECTS
Type Foreman Average Man Loading Labor Factor
Working 2 Men .250
Working 4 Men .375
Working 6 Men .625
Non-Working 10 Men 1.000
Non-Working 16 Men 1.500
x x =
Labor Factor Number of Work Number of Work Days Additional Hours
Hours in One Day in Contract to Estimate for Super-
vision
Example: Simple project to be completed in 160 workdays with an average of 4 men per day with one
of the men being a working foreman.
.250 x 8 x 160 = 320
Labor Factor Number of Work Number of Work Additional Hours
Hours in One Day Days in Contract to Estimate for
Supervision