460-27
HIGH VOLTAGE COPPER COMPRESSION LUGS - 15000V
Average Suggested LABOR HOURS
Size Cost Resale (0-6’) (6-10’) (10-15’) (15-20’)
#4 9.59 38.36 0.25 0.31 0.38 0.44
#2 10.72 42.86 0.40 0.50 0.60 0.70
#1 11.44 45.76 0.40 0.50 0.60 0.70
#1/0 16.22 64.86 0.50 0.63 0.75 0.88
#2/0 16.88 67.52 0.50 0.63 0.75 0.88
#3/0 19.40 74.62 0.65 0.81 0.98 1.14
#4/0 21.22 81.22 0.65 0.81 0.98 1.14
#250 24.19 93.02 0.75 0.94 1.13 1.31
#300 27.70 106.54 0.75 0.94 1.13 1.31
#350 29.09 111.90 0.90 1.13 1.35 1.57
#500 38.28 159.50 1.00 1.25 1.50 1.75
#750 59.88 249.50 1.20 1.50 1.80 2.10
#1000 86.16 358.98 1.50 1.88 2.25 2.63
HIGH VOLTAGE COPPER COMPRESSION SPLICE - 15000V
Average Suggested LABOR HOURS
Size Cost Resale (0-6’) (6-10’) (10-15’) (15-20’)
#4 23.22 89.68 0.50 0.63 0.75 0.88
#2 25.54 98.24 0.60 0.75 0.90 1.05
#1 29.12 112.00 0.70 0.88 1.05 1.23
#1/0 30.86 118.70 0.80 1.00 1.20 1.40
#2/0 33.20 127.68 0.90 1.13 1.35 1.57
#3/0 36.03 138.56 1.00 1.25 1.50 1.75
#4/0 37.80 151.20 1.10 1.38 1.65 1.93
#250 43.24 166.32 1.20 1.50 1.80 2.10
#350 49.17 189.12 1.40 1.75 2.10 2.45
#500 75.61 279.28 1.60 2.00 2.40 2.80
#750 119.31 488.88 2.00 2.50 3.00 3.50
MATERIAL PRICES AND LABOR UNITS ARE PER EACH
AVERAGE COST COLUMN IS A NATIONAL AVERAGE AND SHOULD BE VERIFIED FOR YOUR AREA
NPG