Page 15 - SISK NEWS JULY 2016
P. 15

Minimising Risk
                   It was a resounding success, from the initial stages of
                   fixing steel and formwork, to the logistics on the day.   The Capital Dock project is a
                   The team wasted no time with crane co-ordinator     major project by any measure.
                   Kieran Crowley ensuring the first of six tower cranes   The site will employ up to
                   were erected within twelve hours of the pour finishing.  540 construction workers
                     The main lift and stair cores rising from the basement   at its peak, and take three
                   are formed by slip-form method. The slip form rig is   years to complete. There are
                   divided into three separate levels. The Top Deck where   over 100 design professionals
                   all material is landed by means of a tower crane and   employed, 12 of which will be
                   all cutting of material is carried out. The Working Deck   based full time on site. This
                   is where the majority of the activity is carried out,   immense project will require
                                                                               3
                   for example, the placement of concrete and tying of   35,000m  of concrete, 2,500 tonnes of structural steel
                   steel. Finally the Hanging Deck is where concrete has   and 4,000 tonnes of reinforcing steel which will form
                   passed the 1200mm pan, when it’s still fresh and can   the frames of the buildings.
                   be adapted to achieve an acceptable finish.          In order to mitigate risk, the team have developed a
                                                                       strategy to spread the workload across a number of
                                                                       suppliers and sub-contractors. For example, building
                                                                       frames for the office blocks will use structural steel
                                                                       with precast hollow core floors and slip formed lift
                                                                       and stair-cores. The apartment blocks will use post-
                                                                       tensioned slabs, slip formed lift and stair-cores, and
                                                                       twin-wall precast concrete to rising elements. The third
                                                                       commercial building will be constructed with 500mm
                                                                       deep traditional reinforced concrete slabs.
                                                                        Similarly, three sub-contracts are planned for the
                                                                       façade works. Pre-cast concrete and brick façade
                                                                       panels with integrated windows will be used on the
                                                                       residential apartments, with a unitised façade system
                                                                       by another specialist used on the commercial blocks.














                      On average the slip form rig lifts 3.2m each day.
                                                                       This is a three year project and there are some
                                                                       amazing opportunities awaiting those seeking a new
                                                                       challenge at Sisk. Whilst the core team is in place,
                                                                       many more staff will be required in the coming
                                                                       months. For example, the project requires a full time
                                                                       Quality Manager who co-ordinates the building control
                                                                       process, inspection, test plans and quality cycle.
                                                                        The project team is divided into various disciplines
                                                                       led by Project Director, Declan Kelly. Sean Corr chairs
                                                                       the commercial team, and Shane Glynn the operations
                     (l-r) Ahmed Noureldin – Junior Services Manager,
                                                                       team. The latter of these two is further divided into the
                     Marita Reilly – BCAR Manager, and Ana Arrechea
                     Marfagon – Document Controller
                                                                       engineering team led by Paul Campion, foremen led by
                                                                       Patrick Casey, State Street Bank led by Joe Gartlan, and
                                                                       planning and logistics management led by Earnan Beary.
                                                                        With a number of new labour entering the Irish
                                                                       domestic market, Declan, Shane and the rest of the
                                                                       team have the challenge of embedding the Zero
                                                                       philosophy across the project. But thanks to the
                                                                       careful procurement of reliable subcontractors and
                                                                       potential internal transfers of staff from other areas of
                                                                       the business, this project will certainly be aiming high.
                          Six tower cranes will distribute and lift materials
                          into place
                                                                                               Sisk News  |  July 2016   15



          SISK NEWS JULY 2016 FINAL.indd   15                                                                       05/08/2016   12:23
   10   11   12   13   14   15   16   17   18   19   20