Page 71 - Project+
P. 71

A.  Programming


         B.  Communicating

         C.  Leading

         D.  Problem-solving

     6.  You receive a request from customer service to develop and implement a desktop
         management system for the customer-support staff. What type of project request is
         this?

         A.  Business need

         B.  Market demand

         C.  Legal requirement


         D.  Technological advance

     7.  You are working in a matrix organization. Choose two responses that describe this
         type of structure.

         A.  Project resources are members of another business unit and may or may not be
              able to help you full-time.

         B.  Matrix organizations can be structured as strong, weak, or balanced.

         C.  Project managers have the majority of power in this type of structure.

         D.  This organizational structure is similar to a functional organization.

         E.  Employees are assigned project tasks by their project manager in this type of

              structure.

     8.  A project manager has the most authority under which organizational structure?

         A.  Projectized

         B.  Functional

         C.  Balanced matrix

         D.  Strong matrix

     9.  Your project has expected cash inflows of $7.8 million in today’s dollars. Which
         cash flow technique was used to determine this?

         A.  Discounted cash flow


         B.  IRR

         C.  NPV

         D.  Cost-benefit analysis

    10.  Which of the following are the steps required to validate a project? Choose two.




                                                             71