6. You receive a request from customer service to develop and implement a desktop
management system for the customer-support staff. What type of project request is
this?
A. Business need
B. Market demand
C. Legal requirement
D. Technological advance
7. You are working in a matrix organization. Choose two responses that describe this
type of structure.
A. Project resources are members of another business unit and may or may not be
able to help you full-time.
B. Matrix organizations can be structured as strong, weak, or balanced.
C. Project managers have the majority of power in this type of structure.
D. This organizational structure is similar to a functional organization.
E. Employees are assigned project tasks by their project manager in this type of
structure.
8. A project manager has the most authority under which organizational structure?
A. Projectized
B. Functional
C. Balanced matrix
D. Strong matrix
9. Your project has expected cash inflows of $7.8 million in today’s dollars. Which
cash flow technique was used to determine this?
A. Discounted cash flow
B. IRR
C. NPV
D. Cost-benefit analysis
10. Which of the following are the steps required to validate a project? Choose two.