4. RAB Pembuatan Kapal Pinisi Yacht
RINCIAN ANGGARAN BIAYA
B PEMBANGUNAN KAPAL PINISI YACHT Rp 3.197.975.000
HARGA SATUAN JUMLAH
NO ANGGARAN BIAYA SATUAN VOLUME KETERANGAN
(Rp) (Rp)
A PEKERJAAN KONSTRUKSI 698.300.000
1 Pembuatan Lambung & Bangunan Atas: Pekerjaan Kayu PAKET 1 316.000.000 316.000.000
2 Cat, Anti Fouling, Sealant PAKET 1 43.500.000 43.500.000
3 Balast System PAKET 1 57.000.000 57.000.000
4 Jasa Pembuat Perahu Tradisional & Logistik PAKET 1 281.800.000 281.800.000
B MEKANIKAL 280.000.000
5 Main Engine PAKET 1 79.000.000 79.000.000
6 Main Generator PAKET 1 28.500.000 28.500.000
7 Auxiliary Generator PAKET 1 15.000.000 15.000.000
8 Propulsion System PAKET 1 14.000.000 14.000.000
9 Steering System PAKET 1 15.500.000 15.500.000
10 Plumbing PAKET 1 12.000.000 12.000.000
11 Outfitting PAKET 1 32.000.000 32.000.000
12 Tanks PAKET 1 24.000.000 24.000.000
13 Watermaker PAKET 1 20.000.000 40.000.000
14 Galley Mechanical PAKET 1 20.000.000 20.000.000
C ELECTRICAL 153.000.000
15 Peralatan Kelistrikan PAKET 1 25.000.000
15.000.000
Panel DC *) Detail Biaya Akan
Switch Board 10.000.000
16 Panel Tenaga Surya PAKET 1 25.000.000
Disampaikan Kepada Pihak
a. Panel Surya + kabel (400 WP) 17.000.000
b. Charger Control 8.000.000
17 Outfitting PAKET 1 49.000.000 49.000.000
Sponsor Yang Telah Setuju
18 Turbin Tenaga Bayu + Charger Control PAKET 2 12.000.000 24.000.000
19 VRLA Battery 200AH PAKET 4 7.500.000 30.000.000
D ALAT NAVIGASI DAN KOMUNIKASI 149.500.000
20 Auto Pilot Unit 1 50.000.000 50.000.000
21 Gyro Compas Unit 1 25.000.000 25.000.000
20.000.000
Unit
1
20.000.000
22 Radar Mendukung 1Misi ISSC.
23 Long Rage Tracking & Identification (LRTI) Unit 10.000.000 10.000.000
24 Echo Sounder Unit 1 7.500.000 7.500.000
25 Chart Plotter GPS Map Unit 1 15.000.000 15.000.000 Garmin GPSMAP® 7607xsv
26 VHF Marine Radio Unit 1 12.000.000 12.000.000 Garmin VHF 315 Marine Radio
27 Wind Marine Instrument Unit 1 7.000.000 7.000.000 Garmin GNX™ Wind Marine
28 Water Speed Sensor Unit 2 1.000.000 3.000.000
E SPAR, TIANG LAYAR, LAYAR DAN SISTEM LAYAR 550.000.000
29 Mast, Spar, Sail & Rigging Unit 1 550.000.000 550.000.000
F PEKERJAAN INTERIOR 150.000.000
30 Interior PAKET 1 150.000.000 150.000.000
H OPE, UJI COBA, SEWA, TRANSPORTASI, DAN PERIZINAN 345.000.000
31 Out of Pocket Expenses (OPE) On Site Engineer OB 20 3.000.000 60.000.000
Sewa Area Pamer Selama
32 Sewa Galangan BULAN 12 15.000.000 180.000.000
Setahun dengan Fasilitas
33 Transportasi Orang dan Material PAKET 6 10.000.000 60.000.000
34 Registrasi dan Perizinan PAKET 1 15.000.000 15.000.000
35 Sea Trial PAKET 3 10.000.000 30.000.000
Sub Total 1 2.325.800.000
Detail Design & Enginering, Electrical (D&E, EPC PM FEE = 25%) 581.450.000
Sub Total 2 2.907.250.000
PPN (10%) 290.725.000
Grand Total (Sub Total 1 + 2) 3.197.975.000
Table 12: RAB Pembuatan Kapal Pinisi Yacht