                                            ABC – example 1











             Machine setup-related cost per setup hour = R42 000 / 70  =


             R600 per setup hour





             Cost allocation:

             Product A = R600  per hour x 35 hours = R21 000


             Product B = R600 per hour x 35 hours = R21 000





             Cost per unit:


             Product A = R21 000 / 550 = R38.18 per unit

             Product B = R21 000 / 110 = R190.91 per unit