Risk and the risk management process
1.4 The “as low as reasonably practicable” principles (ALARP)
The ALARP principle expresses a point at which the cost of additional risk
reduction would be grossly disproportionate to the benefits achieved
The ALARP principle is usually applied to safety critical, high integrity systems
where health and safety risks cannot be eliminated e.g. Oil rigs.